Little Llwyn Onn Solar Farm & Battery Storage (9.9 MW)

Little Llwyn Onn Solar Farm & Battery Storage is a 9.9 MW solar farm project in Wrexham, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 March 2023, not yet built; the record was last updated on 24 June 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
approved, not builtstatus in REPD
24 June 2022record last updated
Wrexhamcouncil area

Planning timeline

DateStage
9 June 2022Application submitted
8 March 2023Planning permission granted
8 March 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
approved, not built
Record last updated
24 June 2022
Operator or applicant
Novus Renewable Services Limited
Planning authority
Wrexham
Planning application reference
P/2022/0541
Site area
13.9 ha
Address (REPD)
Little Llwyn Onn, Cefn Road, Llwyn Onn
Council area (by location)
Wrexham
Time to decision
39 weeks
Name in REPD
Little Llwyn Onn - Solar Farm & Battery Storage
REPD reference
11543

The scheme also includes 16 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWrexhamUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused2 of 1412%
Onshore wind refused1 of 145%
Battery storage refused0 of 516%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

UK: all UK planning authorities. Counted under these REPD planning authority names: Newry, Mourne and Downe, Wrexham.

Other large projects within 10 km

ProjectTypeMWStatuskm
Maelor Gasworks Solar Farm & Battery Storagesolar farm5.7approved, not built2.2
Williams Farmsolar farm5operational2.3
Wrexham Social Housing PVrooftop solar5.4operational2.5
Land north of Bryn Lanesolar farm6.4permission expired3.4
Land south of Francis Landsolar farm10permission expired3.8
Land at Borras Hallsolar farm10abandoned4.1
Bronwylfa Road, Rhostyllenbattery storage400application submitted5.6
Plas Power Estate Solar Farmsolar farm57application submitted5.7
Penycae Solar Farmsolar farm5operational8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0342, -2.9544).