Energy Projects Near You

Solar, wind and battery projects near Oswestry (SY11)

24 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY11 (Shropshire): 4 are waiting for a planning decision, 15 approved but not yet running, 1 operational. The largest live scheme is Rednal Airfield, West Felton (300 MW battery storage, approved on 16 April 2026, not yet built), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24projects within 10 km
4awaiting a decision
15approved, not running
1operational

Projects within 10 km of SY11

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowen- Solar Arraysolar farmsolar farm1.9refusedupdated Oct 2025Sep 2025refused Oct 2025Oct 2025Shropshire1.6
Glovers Meadow - Ground Mounted Solar Arraysolar farmsolar farm2application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024Shropshire2.5
Cold Move, Maes-Y-Clawddbattery storagebattery storage1approved, not built may be out of dateupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Shropshire2.8
Ebnal Lodgesolar farmsolar farm5operationalupdated Dec 2017Sep 2015granted Dec 2015Dec 2017Shropshire3.5
Berllandeg Farm, Rhoswielsolar farmsolar farm1.3approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Shropshire5.5
Cefn-Y-Maes Farm, Rhydycroesau Solar Parksolar farmsolar farm1.2approved, not built may be out of dateupdated Oct 2022Jul 2022granted Oct 2022Oct 2022Shropshire6.8
Tramway Farm, Crickheathsolar farmsolar farm1.1application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Shropshire7.0
Rednal Airfield, West Feltonbattery storagebattery storage300approved, not builtupdated Jun 2026May 2025granted Apr 2026Jun 2026Shropshire7.7
Manor Farm, Crickheathsolar farmsolar farm1.8approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Shropshire7.7
Winston Farm, Ellesmere Roadsolar farmsolar farm1.1approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Shropshire8.2
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Robert Jones & Agnes Hunt Orthopaedic Hospitalrooftop solarrooftop solar—approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Shropshire1.6
Robert Jones And Agnes Hunt Orthopaedic Hospitalrooftop solarrooftop solar—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Shropshire1.6
Robert Jones and Agnes Hunt Orthopaedic Hospital, Gobowensolar farmsolar farm0.4application submitted may be out of dateupdated May 2024Apr 2024—May 2024Shropshire1.6
Robert Jones and Agnes Hunt Orthopaedic Hospital, Gobowensolar farmsolar farm0.3approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Shropshire1.6
Robert Jones And Agnes Hunt Orthopaedic Hospital, Gobowensolar farmsolar farm0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Shropshire1.6
Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowenrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Shropshire1.6
Farr & Harris Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Shropshire2.3
Bryn-Y-Plentyn Farmsolar farmsolar farm0.5permission expiredupdated Nov 2019Nov 2018granted Feb 2019Nov 2019Shropshire2.6
Bryn Y Plentyn Farm, Middletonwind turbinewind turbine—refusedupdated Oct 2022Oct 2022refused Dec 2022Oct 2022Shropshire2.8
Cold Move, Maes-Y-Clawddrooftop solarrooftop solar0.8approved, not built may be out of dateupdated Apr 2023Feb 2023granted Apr 2023Apr 2023Shropshire2.8
Trefarclawdd Farm, Tref-Ar-Clawddrooftop solarrooftop solar0.2application submittedJun 2026——Shropshire5.2
Cefn-Y-Maes Farm, Rhydycroesau Solar Parkbattery storagebattery storage—approved, not built may be out of dateupdated Oct 2022Jul 2022granted Oct 2022Oct 2022Shropshire6.8
Cefn y Maes Community Renewable Energy Parkbattery storagebattery storage0.5permission expiredupdated Feb 2020Mar 2017—Feb 2020Powys8.1
Plas Yolyn Solar Parksolar farmsolar farm—approved, not builtupdated May 2024Nov 2023granted May 2024May 2024Shropshire8.1

Distance from the average position of the SY11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1337119.4
Rooftop solar514001.2
Wind turbine100010
Battery storage50400301

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SY11, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.