Berrington Farm (30 MW solar farm)

Berrington Farm is a 30 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2025, not yet built; the record was last updated on 20 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
20 May 2025record last updated
Shropshirecouncil area

Planning timeline

DateStage
27 September 2022Application submitted
26 March 2024Refused by the planning authority
2 May 2025Planning permission granted
2 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
20 May 2025
Operator or applicant
Econergy International Limited
Planning authority
Shropshire
Planning application reference
22/04355/FUL
Site area
44.1 ha
Address (REPD)
The West Of Berrington
Council area (by location)
Shropshire
Time to decision
135 weeks
Name in REPD
Berrington Farm - Solar Array
REPD reference
12266

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Condover (Green Farm)solar farm10.2operational1.5
Condover Airfieldsolar farm12.3operational2.9
Pitchfordsolar farm10.2operational3.6
Pelham Road, Upton Magnabattery storage100application submitted5.9
Battery Energy Storagebattery storage100application submitted6.1
Bridge Farm, Uffingtonbattery storage8approved, not built6.6
Haughmond Quarry - Uffington Solar Farmsolar farm25refused8.3
Church Farm, Withington Solar Farmsolar farm25approved, not built8.5
Sundorne Grovesolar farm20operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6544, -2.7075).