Energy Projects Near You

Bridge Farm, Uffington (8 MW battery storage)

Bridge Farm, Uffington is an 8 MW battery storage project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 April 2023, not yet built; the record was last updated on 22 January 2024. REPD also records that the planning permission expired on 19 April 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWbattery storage
approved, not builtmay be out of datestatus in REPD
22 January 2024record last updated
Shropshirecouncil area

REPD also records that the planning permission expired on 19 April 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
27 January 2023Application submitted
19 April 2023Planning permission granted
19 April 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
8 MW
Status (REPD)
approved, not built
Record last updated
22 January 2024
Operator or applicant
Hydrock
Planning authority
Shropshire
Planning application reference
23/00254/FUL
Address (REPD)
The S/O Uffington Shrewsbury
Council area (by location)
Shropshire
Time to decision
12 weeks
Name in REPD
Bridge Farm, Uffington - Battery Energy Storage
REPD reference
13161

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Battery Energy Storagebattery storage100application submitted0.6
Haughmond Quarry - Uffington Solar Farmsolar farm25refused1.6
Sundorne Grovesolar farm20operational2.6
Pelham Road, Upton Magnabattery storage100application submitted2.6
Church Farm, Withington Solar Farmsolar farm25approved, not built4.5
Myttons Solar Farmsolar farm49.9approved, not built4.9
Berrington Farmsolar farm30approved, not built6.6
Condover (Green Farm)solar farm10.2operational6.8
Tiddiecross Solar Farmsolar farm10.5operational8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7135, -2.6937).