Tiddiecross Solar Farm (10.5 MW)

Tiddiecross Solar Farm is a 10.5 MW solar farm project in Telford and Wrekin, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
Telford and Wrekincouncil area

Planning timeline

DateStage
10 September 2014Application submitted
7 January 2015Planning permission granted
8 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
10.5 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
Vogt Solar
Planning authority
Telford and Wrekin
Planning application reference
TWC/2014/0810
Site area
13.1 ha
Address (REPD)
Land adjacent to Tiddiecross, Charlton, Telford
Council area (by location)
Telford and Wrekin
Time to decision
17 weeks
REPD reference
4858

Who decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiddiecross Solar Farm & Battery Storagesolar farm14approved, not built<0.1
Rushmoor Lane Farm (Cheshire Coppice)solar farm5operational3.0
Church Farm, Withington Solar Farmsolar farm25approved, not built3.6
Steeraway Farm Solar Farmsolar farm30under construction4.8
New Works Lane Solar Farmsolar farm30application submitted5.3
Pelham Road, Upton Magnabattery storage100application submitted5.9
High Ercall Solar Farmsolar farm49.9approved, not built7.2
Myttons Solar Farmsolar farm49.9approved, not built7.4
Battery Energy Storagebattery storage100application submitted7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7035, -2.5747).