Tiddiecross Solar Farm & Battery Storage (14 MW)

Tiddiecross Solar Farm & Battery Storage is a 14 MW solar farm project in Telford and Wrekin, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 6 June 2025, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Telford and Wrekincouncil area

Planning timeline

DateStage
11 December 2024Application submitted
6 June 2025Planning permission granted

Project details

Technology
solar farm
Capacity
14 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Boultbee Brooks Renewables Walkford Moor Limited
Planning authority
Telford and Wrekin
Planning application reference
TWC/2024/0909
Site area
19.8 ha
Address (REPD)
N/O Tiddiecross Lane, Telford
Council area (by location)
Telford and Wrekin
Time to decision
25 weeks
Contracts for Difference
AR7a
Name in REPD
Tiddiecross Lane, Charlton - Tiddiecross Solar Farm & Battery Storage
REPD reference
17853

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tiddiecross Solar Farmsolar farm10.5operational<0.1
Rushmoor Lane Farm (Cheshire Coppice)solar farm5operational3.0
Church Farm, Withington Solar Farmsolar farm25approved, not built3.6
Steeraway Farm Solar Farmsolar farm30under construction4.8
New Works Lane Solar Farmsolar farm30application submitted5.3
Pelham Road, Upton Magnabattery storage100application submitted5.9
High Ercall Solar Farmsolar farm49.9approved, not built7.2
Myttons Solar Farmsolar farm49.9approved, not built7.4
Battery Energy Storagebattery storage100application submitted7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7035, -2.5747).