High Ercall Solar Farm (49.9 MW)

High Ercall Solar Farm is a 49.9 MW solar farm project in Telford and Wrekin, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 August 2023, not yet built; the record was last updated on 18 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
18 September 2023record last updated
Telford and Wrekincouncil area

Planning timeline

DateStage
26 January 2023Application submitted
22 August 2023Planning permission granted
22 August 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
18 September 2023
Operator or applicant
Assured Asset Solar 1 Limited
Planning authority
Telford and Wrekin
Planning application reference
TWC/2023/0064
Site area
89.5 ha
Address (REPD)
East & South of Angel Centre, Osbaston
Council area (by location)
Telford and Wrekin
Time to decision
30 weeks
REPD reference
13183

Who decides

ApplicationsTelford and WrekinUK
Decided applications (solar, wind, battery)3410,236
Refused6 (18%)19%
Solar refused1 of 2512%
Battery storage refused5 of 916%
Median time from submission to decision12.7 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Myttons Solar Farmsolar farm49.9approved, not built4.7
Rushmoor Lane Farm (Cheshire Coppice)solar farm5operational5.1
The Old Airfield Solar Farmsolar farm49approved, not built6.5
Church Farm, Withington Solar Farmsolar farm25approved, not built6.6
Tiddiecross Solar Farm & Battery Storagesolar farm14approved, not built7.2
Tiddiecross Solar Farmsolar farm10.5operational7.2
Haughmond Quarry - Uffington Solar Farmsolar farm25refused8.0
Sundorne Grovesolar farm20operational8.8
Pelham Road, Upton Magnabattery storage100application submitted9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.7674, -2.589).