Energy Projects Near You

Solar, wind and battery projects near Much Wenlock (TF13)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TF13 (Shropshire): 4 approved but not yet running, 1 operational. The largest live scheme is Buildwas (100 MW battery storage, approved on 22 April 2026, not yet built), 8.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
4approved, not running
1operational

Projects within 10 km of TF13

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Buildwasbattery storagebattery storage100approved, not builtupdated Jun 2026Apr 2025granted Apr 2026Jun 2026Shropshire8.0
Hollydale, Buildwas Roadbattery storagebattery storage40approved, not builtupdated Feb 2024Mar 2023granted Jan 2024Feb 2024Shropshire8.0
Upper Meadowley Farmsolar farmsolar farm10.7operationalupdated Oct 2017Aug 2014granted Nov 2015Oct 2017Shropshire8.3
Criddon Hall Farmwind farmwind farm3application withdrawnupdated Jun 2014May 2013—Jun 2014Shropshire8.9
Oakridge Farmsolar farmsolar farm2abandonedupdated Mar 2015Mar 2011granted Jun 2011Mar 2015Shropshire9.2
High Trees Farmsolar farmsolar farm3.8refused on appealupdated Oct 2015May 2014refused Jan 2015Oct 2015Shropshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Syspal, Cockshutt Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Dec 2022granted Jan 2023Jan 2023Shropshire8.4
Buildwas Bankbattery storagebattery storage—approved, not builtupdated Sep 2025Sep 2023granted Aug 2025Sep 2025Telford and Wrekin9.9

Distance from the average position of the TF13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300110
Rooftop solar101000.2
Wind farm100000
Battery storage30300140

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.