Upper Meadowley Farm (10.7 MW solar farm)

Upper Meadowley Farm is a 10.7 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 4 October 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.7 MWsolar farm
operationalstatus in REPD
4 October 2017record last updated
Shropshirecouncil area

Planning timeline

DateStage
28 August 2014Application submitted
12 November 2015Planning permission granted
31 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
10.7 MW
Status (REPD)
operational
Record last updated
4 October 2017
Operator or applicant
GDL Upper Meadowley
Planning authority
Shropshire
Planning application reference
14/03933/FUL
Site area
20.1 ha
Address (REPD)
Upper Meadowley Farm, Upton Cresset, Bridgnorth, Shropshire
Council area (by location)
Shropshire
Time to decision
63 weeks
REPD reference
2272

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Swancote Farm -Solar Panelssolar farm5approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5295, -2.4909).