Swancote Farm -Solar Panels (5 MW)

Swancote Farm -Solar Panels is a 5 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 January 2025, not yet built; the record was last updated on 27 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtstatus in REPD
27 January 2025record last updated
Shropshirecouncil area

Planning timeline

DateStage
17 October 2024Application submitted
21 January 2025Planning permission granted
21 January 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
27 January 2025
Operator or applicant
Swancote Energy Limited
Planning authority
Shropshire
Planning application reference
24/04003/FUL
Site area
6.7 ha
Address (REPD)
Nw/O Swancote Farm, Swancote, Bridgnorth
Council area (by location)
Shropshire
Time to decision
14 weeks
REPD reference
17453

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upper Meadowley Farmsolar farm10.7operational7.6
Astley Solar Farmsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5433, -2.3812).