Energy Projects Near You

Solar, wind and battery projects near Bridgnorth (WV15)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WV15 (Shropshire): 2 approved but not yet running, 2 operational. The largest live scheme is Swancote Farm -Solar Panels (5 MW solar farm, approved on 21 January 2025, not yet built), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
2approved, not running
2operational

Projects within 10 km of WV15

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Swancote Farm -Solar Panelssolar farmsolar farm5approved, not builtupdated Jan 2025Oct 2024granted Jan 2025Jan 2025Shropshire3.2
High Trees Farmsolar farmsolar farm3.8refused on appealupdated Oct 2015May 2014refused Jan 2015Oct 2015Shropshire6.2
Astley Solar Farmsolar farmsolar farm5operationalupdated May 2017May 2015granted Sep 2015May 2017Shropshire6.3
Upper Meadowley Farmsolar farmsolar farm10.7operationalupdated Oct 2017Aug 2014granted Nov 2015Oct 2017Shropshire8.1
Criddon Hall Farmwind farmwind farm3application withdrawnupdated Jun 2014May 2013—Jun 2014Shropshire8.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bridgnorth Garden Centre - Storage Warehouserooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2023Sep 2022granted Mar 2023Apr 2023South Staffordshire9.1

Distance from the average position of the WV15 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401215
Rooftop solar101000
Wind farm100000

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WV15, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.