Energy Projects Near You

Solar, wind and battery projects near Bewdley (DY12)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DY12 (Wyre Forest): 1 is waiting for a planning decision, 5 approved but not yet running, 1 operational. The largest live scheme is John Tainton, Frederick Road (0.8 MW rooftop solar, approved on 12 May 2025, not yet built), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
1awaiting a decision
5approved, not running
1operational

Projects within 10 km of DY12

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Astley Solar Farmsolar farmsolar farm5operationalupdated May 2017May 2015granted Sep 2015May 2017Shropshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Midlands Safari Park Solar developmentsolar farmsolar farm0.5approved, not builtupdated Jul 2024Sep 2023granted Jul 2024Jul 2024Wyre Forest2.9
Parker Place, Firs Industrial Estate, Unit 8rooftop solarrooftop solar0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Wyre Forest5.4
Morrisons Superstorerooftop solarrooftop solar0.5approved, not builtupdated Mar 2022Feb 2022granted Mar 2022Mar 2022Wyre Forest5.9
John Tainton, Frederick Roadrooftop solarrooftop solar0.8approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Wyre Forest6.4
Conveyor Units, Sandy Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Wyre Forest7.7
Lincomb Farmbattery storagebattery storage—application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023Wychavon9.2

Distance from the average position of the DY12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.5
Rooftop solar404001.7
Battery storage110000

MW in pipeline: pending, approved and under-construction capacity.

How Wyre Forest decides solar, wind and battery applications

Wyre Forest has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Wyre Forest

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DY12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.