Energy Projects Near You

Solar, wind and battery projects near Kidderminster (DY10)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DY10 (Wyre Forest): 4 are waiting for a planning decision, 7 approved but not yet running. The largest live scheme is Fibden Farm (40 MW solar farm, application submitted on 14 June 2024, no decision recorded; REPD status may be out of date), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
4awaiting a decision
7approved, not running
0operational

Projects within 10 km of DY10

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Roundhill Sewage Works Wind Turbineswind farmwind farm6.8refused on appealupdated Oct 2013Apr 2010refused Jun 2010Oct 2013South Staffordshire7.7
Norchard Farmsolar farmsolar farm8.8approved, not builtupdated Jun 2025Jul 2023granted Oct 2024Jun 2025Wychavon8.0
Crossway Green, Ombersleysolar farmsolar farm18application submitted may be out of dateupdated Oct 2023Sep 2023—Oct 2023Wychavon9.7
Fibden Farmsolar farmsolar farm40application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024Wychavon9.7
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morrisons Superstorerooftop solarrooftop solar0.5approved, not builtupdated Mar 2022Feb 2022granted Mar 2022Mar 2022Wyre Forest1.5
John Tainton, Frederick Roadrooftop solarrooftop solar0.8approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Wyre Forest2.7
Parker Place, Firs Industrial Estate, Unit 8rooftop solarrooftop solar0.3approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Wyre Forest4.2
West Midlands Safari Park Solar developmentsolar farmsolar farm0.5approved, not builtupdated Jul 2024Sep 2023granted Jul 2024Jul 2024Wyre Forest4.7
Sion House, Sion Hillsolar farmsolar farm0.2application withdrawnupdated Jun 2026Dec 2025—Jun 2026Wyre Forest4.8
Roundhill Anaerobic Digestion Facility, Lloyd Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025South Staffordshire7.0
Conveyor Units, Sandy Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Wyre Forest7.1
Lincomb Farmbattery storagebattery storage—application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023Wychavon8.3
Fibden Farmbattery storagebattery storage—application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024Wychavon9.7

Distance from the average position of the DY10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5220067.2
Rooftop solar505001.9
Wind farm100010
Battery storage220000

MW in pipeline: pending, approved and under-construction capacity.

How Wyre Forest decides solar, wind and battery applications

Wyre Forest has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Wyre Forest

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DY10, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.