Norchard Farm (8.8 MW solar farm)

Norchard Farm is an 8.8 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 October 2024, not yet built; the record was last updated on 9 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.8 MWsolar farm
approved, not builtstatus in REPD
9 June 2025record last updated
Wychavoncouncil area

Planning timeline

DateStage
19 July 2023Application submitted
11 October 2024Planning permission granted
11 October 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
8.8 MW
Status (REPD)
approved, not built
Record last updated
9 June 2025
Operator or applicant
Norchard Solar Farm Limited
Planning authority
Wychavon
Planning application reference
W/23/01483/FUL
Site area
11.9 ha
Address (REPD)
Norchard Farm, Norchard Lane, Crossway Green, Stourport-On-Severn, Hereford and Worcester
Council area (by location)
Wychavon
Time to decision
64 weeks
REPD reference
6550

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crossway Green, Ombersleysolar farm18application submitted1.7
Doverdale Solar Farm & Battery Storagesolar farm49.9operational2.9
Doverdale Solar Farm & Battery Storagebattery storage49.9operational2.9
Fibden Farmsolar farm40application submitted3.9
Fibden Farm, Hampton Lovettsolar farm40approved, not built4.8
Sinton Green Solar Farmsolar farm21refused8.4
Rectory Farm, Rectory Lanebattery storage30approved, not built8.5
Rectory Farmsolar farm8.9refused on appeal8.7
Land at Rectory Farmsolar farm8.9application withdrawn8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3153, -2.2267).