Crossway Green, Ombersley (18 MW solar farm)
Crossway Green, Ombersley is an 18 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 September 2023, no decision recorded; the record was last updated on 20 October 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
| Date | Stage |
|---|---|
| 28 September 2023 | Application submitted |
Project details
- Technology
- solar farm
- Capacity
- 18 MW
- Status (REPD)
- application submitted
- Record last updated
- 20 October 2023
- Operator or applicant
- Tyler Hill Solar Limited
- Planning authority
- Wychavon
- Planning application reference
- W/23/01894/FUL
- Site area
- 26.6 ha
- Address (REPD)
- (OS 8426 6690) Crossway Green, Ombersley, Stourport on Severn
- Council area (by location)
- Wychavon
- Name in REPD
- Crossway Green, Ombersley - Solar Panels
- REPD reference
- 14001
Who decides
| Applications | Wychavon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 50 | 10,236 |
| Refused | 3 (6%) | 19% |
| Solar refused | 2 of 34 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 0 of 14 | 16% |
| Median time from submission to decision | 20.5 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Norchard Farm | solar farm | 8.8 | approved, not built | 1.7 |
| Doverdale Solar Farm & Battery Storage | solar farm | 49.9 | operational | 1.8 |
| Doverdale Solar Farm & Battery Storage | battery storage | 49.9 | operational | 1.8 |
| Fibden Farm | solar farm | 40 | application submitted | 4.0 |
| Fibden Farm, Hampton Lovett | solar farm | 40 | approved, not built | 4.9 |
| Sinton Green Solar Farm | solar farm | 21 | refused | 6.8 |
| Land at Winshenford | solar farm | 7 | refused | 7.7 |
| Fitcher Brook Solar Farm | solar farm | 19 | application submitted | 8.7 |
| Rectory Farm, Rectory Lane | battery storage | 30 | approved, not built | 8.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2998, -2.23).