Energy Projects Near You

Rectory Farm, Rectory Lane (30 MW battery storage)

Rectory Farm, Rectory Lane is a 30 MW battery storage project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 February 2023, not yet built; the record was last updated on 25 July 2025. REPD also records that the planning permission expired on 20 February 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtmay be out of datestatus in REPD
25 July 2025record last updated
Wychavoncouncil area

REPD also records that the planning permission expired on 20 February 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
16 November 2022Application submitted
20 February 2023Planning permission granted
20 February 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
25 July 2025
Operator or applicant
Tag Energy
Planning authority
Wychavon
Planning application reference
W/22/02326/FUL
Address (REPD)
Rectory Farm Rectory Lane Upton Warren
Council area (by location)
Wychavon
Time to decision
14 weeks
Name in REPD
Rectory Farm, Rectory Lane - Battery Storage
REPD reference
11905

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Rectory Farmsolar farm8.9application withdrawn0.4
Rectory Farmsolar farm8.9refused on appeal0.7
Foxwalks Farm, Grafton Lane Solar Farmsolar farm49.9approved, not built1.5
Foxwalks Solar Farm - Extensionsolar farm13application submitted3.3
Fibden Farm, Hampton Lovettsolar farm40approved, not built3.8
Fibden Farmsolar farm40application submitted4.7
Doverdale Solar Farm & Battery Storagebattery storage49.9operational7.2
Doverdale Solar Farm & Battery Storagesolar farm49.9operational7.2
Norchard Farmsolar farm8.8approved, not built8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3088, -2.1024).