Foxwalks Farm, Grafton Lane Solar Farm (49.9 MW)

Foxwalks Farm, Grafton Lane Solar Farm is a 49.9 MW solar farm project in Bromsgrove, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 July 2024, not yet built; the record was last updated on 17 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
17 February 2026record last updated
Bromsgrovecouncil area

Planning timeline

DateStage
13 September 2023Application submitted
18 July 2024Planning permission granted
18 July 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 February 2026
Operator or applicant
Spring Dev 10 Limited
Planning authority
Bromsgrove
Planning application reference
23/00896/FUL
Site area
40.6 ha
Address (REPD)
Foxwalks Farm Grafton Lane
Council area (by location)
Bromsgrove
Time to decision
44 weeks
Contracts for Difference
AR7a
Name in REPD
Foxwalks Farm, Grafton Lane - Solar Farm
REPD reference
14914

Who decides

Bromsgrove has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Rectory Farmsolar farm8.9refused on appeal0.7
Land at Rectory Farmsolar farm8.9application withdrawn1.1
Rectory Farm, Rectory Lanebattery storage30approved, not built1.5
Foxwalks Solar Farm - Extensionsolar farm13application submitted1.9
Fibden Farm, Hampton Lovettsolar farm40approved, not built4.6
Fibden Farmsolar farm40application submitted5.4
Doverdale Solar Farm & Battery Storagebattery storage49.9operational8.0
Doverdale Solar Farm & Battery Storagesolar farm49.9operational8.0
Norchard Farmsolar farm8.8approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3217, -2.0974).