Energy Projects Near You

Doverdale Solar Farm & Battery Storage (49.9 MW, REPD 8528)

Doverdale Solar Farm & Battery Storage is a 49.9 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2025; the record was last updated on 24 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
24 April 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
22 June 2021Application submitted
13 January 2022Planning permission granted
1 December 2025Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
24 April 2026
Operator or applicant
RWE
Planning authority
Wychavon
Planning application reference
21/01363/FUL
Site area
63.4 ha
Address (REPD)
Northwest of Doverdale, Southall Lane, Doverdale, Worcester
Council area (by location)
Wychavon
Time to decision
29 weeks
Contracts for Difference
AR4
Name in REPD
Doverdale - Solar Farm & Battery Storage
REPD reference
8528

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Doverdale Solar Farm & Battery Storagebattery storage49.9operational<0.1
Crossway Green, Ombersleysolar farm18application submitted1.8
Fibden Farmsolar farm40application submitted2.7
Norchard Farmsolar farm8.8approved, not built2.9
Fibden Farm, Hampton Lovettsolar farm40approved, not built3.5
Sinton Green Solar Farmsolar farm21refused7.1
Rectory Farm, Rectory Lanebattery storage30approved, not built7.2
Land at Rectory Farmsolar farm8.9application withdrawn7.6
Rectory Farmsolar farm8.9refused on appeal7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2926, -2.2056).