Solar, wind and battery projects near Worcester (WR4)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WR4 (Worcester): 5 are waiting for a planning decision, 12 approved but not yet running, 5 operational. The largest live scheme is Fitcher Brook Solar Farm (19 MW solar farm, application submitted on 19 December 2023, no decision recorded; REPD status may be out of date), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
5awaiting a decision
12approved, not running
5operational

Projects within 10 km of WR4

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Droitwich Road, Martin Hussingtree Solar Parksolar farmsolar farm4application submitted may be out of dateupdated Apr 2022May 2023—Apr 2022Worcester2.4
Pershore Lane, Tibbertonbattery storagebattery storage14approved, not builtupdated Oct 2023Dec 2022granted Oct 2023Oct 2023Wychavon2.8
Fitcher Brook Solar Farmsolar farmsolar farm19application submitted may be out of dateupdated Jan 2024Dec 2023—Jan 2024Malvern Hills4.9
Norton Fields Farmwind turbinewind turbine1.3operationalupdated Jun 2016Jul 2014granted Dec 2014Jun 2016Wychavon5.4
Mucknell Farm Lane, Stoulton Solar Farmsolar farmsolar farm1refusedupdated May 2024Oct 2022refused May 2024May 2024Wychavon5.8
Otherton Farmsolar farmsolar farm4operationalupdated Aug 2017Jul 2015granted Dec 2015Aug 2017Malvern Hills6.9
Sinton Green Solar Farmsolar farmsolar farm21refusedupdated Jun 2021Oct 2021refused Jan 2023Jun 2021Malvern Hills7.6
Deritend Precision Casting, Vines Lanerooftop solarrooftop solar1.2approved, not builtupdated Jan 2026Mar 2025granted May 2025Jan 2026Wychavon8.1
Land at Winshenfordsolar farmsolar farm7refusedupdated Jan 2016Jul 2015refused Dec 2015Jan 2016Malvern Hills8.4
Allsetts Farmsolar farmsolar farm6.8permission expiredupdated Sep 2018Mar 2015granted Aug 2015Sep 2018Malvern Hills8.7
Chapel Hill Solar Arrayssolar farmsolar farm49.9refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills8.9
Land at Woodhall Farmsolar farmsolar farm45refused on appealupdated Feb 2017Dec 2014refused Aug 2015Feb 2017Malvern Hills9.1
Doverdale Solar Farm & Battery Storagesolar farmsolar farm49.9operationalupdated Apr 2026Jun 2021granted Jan 2022Apr 2026Wychavon9.9
Doverdale Solar Farm & Battery Storagebattery storagebattery storage49.9operationalupdated Apr 2026Jun 2021granted Jan 2022Apr 2026Wychavon9.9
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bosch Thermotecnology UK Limited, Cotswold Wayrooftop solarrooftop solar0.9approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022Worcester1.4
Tudor Grange Academy, Bilford Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Oct 2023granted Apr 2024Apr 2024Worcester1.5
Perdiswell Leisure Centre, Bilford Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Aug 2024granted Sep 2024Sep 2024Worcester1.8
Clayfield Road, Worcester Six Business Parkrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024Jun 2024granted Jul 2024Jul 2024Wychavon2.0
Hornhill Road, Nunnery Wayrooftop solarrooftop solar0.1approved, not builtupdated May 2026Mar 2026granted Apr 2026May 2026Worcester2.1
St Martins Gate Car Park, St Martins Gate Solar PV Systemsrooftop solarrooftop solar—application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024Worcester2.3
David Lloyd Leisure, Warriors Wayrooftop solarrooftop solar0.4approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Wychavon2.3
Droitwich Road, Martin Hussingtree Solar Parkbattery storagebattery storage—application submitted may be out of dateupdated May 2023May 2023—May 2023Worcester2.4
Worcester Rugby Football Club, Hindlip - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Wychavon2.5
Henwick Groverooftop solarrooftop solar—operationalupdated Jan 2022Sep 2021granted Jan 2022Jan 2022Worcester3.7
Vandemoortele Worcester Solar Farmsolar farmsolar farm0.6application submittedupdated Jan 2025Oct 2024—Jan 2025Malvern Hills4.7
Vamix Factory, Martley Roadsolar farmsolar farm0.4approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Malvern Hills4.7
Copcut Lane, Copcut -Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Dec 2025Sep 2025granted Oct 2025Dec 2025Wychavon4.9
Fircone Farm, Church Road - 249KW Solar Panelssolar farmsolar farm0.2application withdrawnupdated Jun 2026Apr 2025—Jun 2026Wychavon5.1
Woodbury Lane, Nortonrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Apr 2024Apr 2024Wychavon5.3
Chapel Hillbattery storagebattery storage—refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills8.9

Distance from the average position of the WR4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm13312524
Rooftop solar1018103.7
Wind turbine100100
Battery storage6131114.4

MW in pipeline: pending, approved and under-construction capacity.

How Worcester decides solar, wind and battery applications

Worcester has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Worcester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WR4, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.