Sinton Green Solar Farm (21 MW)

Sinton Green Solar Farm is a 21 MW solar farm project in Malvern Hills, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 January 2023; the record was last updated on 11 June 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21 MWsolar farm
refusedstatus in REPD
11 June 2021record last updated
Malvern Hillscouncil area

Planning timeline

DateStage
11 October 2021Application submitted
25 January 2023Refused by the planning authority

Project details

Technology
solar farm
Capacity
21 MW
Status (REPD)
refused
Record last updated
11 June 2021
Operator or applicant
BRL Solar UK Limited
Planning authority
Malvern Hills
Planning application reference
21/01846/FUL
Site area
36.0 ha
Address (REPD)
Os 8036 6145 Sinton Green, Hallow, Worcester
Council area (by location)
Malvern Hills
Time to decision
67 weeks
REPD reference
9133

Who decides

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Winshenfordsolar farm7refused1.3
Fitcher Brook Solar Farmsolar farm19application submitted3.0
Land at Woodhall Farmsolar farm45refused on appeal4.2
Allsetts Farmsolar farm6.8permission expired4.8
Crossway Green, Ombersleysolar farm18application submitted6.8
Doverdale Solar Farm & Battery Storagesolar farm49.9operational7.1
Doverdale Solar Farm & Battery Storagebattery storage49.9operational7.1
Norchard Farmsolar farm8.8approved, not built8.4
Pershore Lane, Tibbertonbattery storage14approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2462, -2.2768).