Land at Winshenford (7 MW solar farm)

Land at Winshenford is a 7 MW solar farm project in Malvern Hills, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 December 2015; the record was last updated on 6 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
refusedstatus in REPD
6 January 2016record last updated
Malvern Hillscouncil area

Planning timeline

DateStage
31 July 2015Application submitted
9 December 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
refused
Record last updated
6 January 2016
Operator or applicant
Elgar Middleton
Planning authority
Malvern Hills
Planning application reference
15/01033/FUL
Site area
12.0 ha
Address (REPD)
Land at Green Farm and Bush Farm, Monkwood Green, Hallow, Worcester
Council area (by location)
Malvern Hills
Time to decision
19 weeks
REPD reference
5541

Who decides

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sinton Green Solar Farmsolar farm21refused1.3
Land at Woodhall Farmsolar farm45refused on appeal3.1
Fitcher Brook Solar Farmsolar farm19application submitted3.6
Allsetts Farmsolar farm6.8permission expired3.9
Crossway Green, Ombersleysolar farm18application submitted7.7
Doverdale Solar Farm & Battery Storagebattery storage49.9operational8.2
Doverdale Solar Farm & Battery Storagesolar farm49.9operational8.2
Norchard Farmsolar farm8.8approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2431, -2.2953).