Land at Woodhall Farm (45 MW solar farm)

Land at Woodhall Farm is a 45 MW solar farm project in Malvern Hills, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 February 2017; the record was last updated on 28 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWsolar farm
refused on appealstatus in REPD
28 February 2017record last updated
Malvern Hillscouncil area

Planning timeline

DateStage
10 December 2014Application submitted
12 August 2015Refused by the planning authority
17 February 2016Appeal lodged
23 February 2017Appeal refused

Project details

Technology
solar farm
Capacity
45 MW
Status (REPD)
refused on appeal
Record last updated
28 February 2017
Operator or applicant
Kronos Solar
Planning authority
Malvern Hills
Planning application reference
14/01658/FUL
Appeal reference
APP/J1860/W/16/3142020
Address (REPD)
Land at Woodhall Farm, Wichenford, Worcester
Council area (by location)
Malvern Hills
Time to decision
35 weeks
REPD reference
4875

Who decides

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Allsetts Farmsolar farm6.8permission expired1.0
Land at Winshenfordsolar farm7refused3.1
Sinton Green Solar Farmsolar farm21refused4.2
Fitcher Brook Solar Farmsolar farm19application submitted4.5
Chapel Hill Solar Arrayssolar farm49.9refused7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2198, -2.3199).