Energy Projects Near You

Solar, wind and battery projects near Worcester (WR6)

10 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WR6 (Malvern Hills): 2 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is Fitcher Brook Solar Farm (19 MW solar farm, application submitted on 19 December 2023, no decision recorded; REPD status may be out of date), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10projects within 10 km
2awaiting a decision
2approved, not running
1operational

Projects within 10 km of WR6

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Woodhall Farmsolar farmsolar farm45refused on appealupdated Feb 2017Dec 2014refused Aug 2015Feb 2017Malvern Hills4.4
Allsetts Farmsolar farmsolar farm6.8permission expiredupdated Sep 2018Mar 2015granted Aug 2015Sep 2018Malvern Hills5.0
Land at Winshenfordsolar farmsolar farm7refusedupdated Jan 2016Jul 2015refused Dec 2015Jan 2016Malvern Hills6.1
Sinton Green Solar Farmsolar farmsolar farm21refusedupdated Jun 2021Oct 2021refused Jan 2023Jun 2021Malvern Hills7.4
Otherton Farmsolar farmsolar farm4operationalupdated Aug 2017Jul 2015granted Dec 2015Aug 2017Malvern Hills8.2
Stockton Court Farmsolar farmsolar farm5application withdrawnupdated Jun 2017Apr 2016—Jun 2017Malvern Hills8.4
Fitcher Brook Solar Farmsolar farmsolar farm19application submitted may be out of dateupdated Jan 2024Dec 2023—Jan 2024Malvern Hills8.8
Stockton Court farmsolar farmsolar farm5approved, not built may be out of dateupdated Sep 2019Aug 2015granted Apr 2017Sep 2019Malvern Hills9.0
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Vandemoortele Worcester Solar Farmsolar farmsolar farm0.6application submittedupdated Jan 2025Oct 2024—Jan 2025Malvern Hills8.9
Vamix Factory, Martley Roadsolar farmsolar farm0.4approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Malvern Hills8.9

Distance from the average position of the WR6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm10221325

MW in pipeline: pending, approved and under-construction capacity.

How Malvern Hills decides solar, wind and battery applications

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Malvern Hills

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WR6, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.