Stockton Court Farm (5 MW solar farm)
Stockton Court Farm is a 5 MW solar farm project in Malvern Hills, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 25 May 2017; the record was last updated on 1 June 2017.
5 MWsolar farm
application withdrawnstatus in REPD
1 June 2017record last updated
Malvern Hillscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 21 April 2016 | Application submitted |
| 25 May 2017 | Application withdrawn |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 1 June 2017
- Operator or applicant
- Renewable Power Exchange
- Planning authority
- Malvern Hills
- Planning application reference
- 16/00678/FUL
- Site area
- 7.7 ha
- Address (REPD)
- Court Farm, Stockton Court, Stockton,
- Council area (by location)
- Malvern Hills
- REPD reference
- 6183
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Stockton Court farm 15/01017/FUL | 5 | 11 August 2015 | approved on 5 April 2017, not yet built |
Who decides
| Applications | Malvern Hills | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 14 | 10,236 |
| Refused | 7 (50%) | 19% |
| Solar refused | 5 of 10 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 20.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Stockton Court farm | solar farm | 5 | approved, not built | 0.8 |
| The Waddings, Knighton-On-Teme | battery storage | 60 | application submitted | 8.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3024, -2.418).