Energy Projects Near You

Solar, wind and battery projects near Malvern (WR14)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WR14 (Malvern Hills): 3 approved but not yet running, 2 operational. The largest live scheme is Whitehouse Farm Energy Barn (40 MW battery storage, approved on 29 November 2017, not yet built), 4.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
3approved, not running
2operational

Projects within 10 km of WR14

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Havenwind turbinewind turbine1.2operationalupdated Sep 2005Dec 2002granted Feb 2003Sep 2005Malvern Hills1.6
Whitehouse Farm Energy Barnbattery storagebattery storage40approved, not builtupdated Jun 2020Oct 2017granted Nov 2017Jun 2020Malvern Hills4.1
Chapel Hill Solar Arrayssolar farmsolar farm49.9refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills4.6
Otherton Farmsolar farmsolar farm4operationalupdated Aug 2017Jul 2015granted Dec 2015Aug 2017Malvern Hills8.2
Sinton End Farm, Acton Beauchamp Solar Farmsolar farmsolar farm20refusedupdated Dec 2025Jul 2025refused Oct 2025Dec 2025Herefordshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Malvern Splash, Priory Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024Malvern Hills0.6
Chapel Hillbattery storagebattery storage—refusedupdated Dec 2025Jan 2025refused Nov 2025Dec 2025Malvern Hills4.6
Millers Court Farm, Birts Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Malvern Hills9.8

Distance from the average position of the WR14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300120
Rooftop solar202000.4
Wind turbine100100
Battery storage2010140

MW in pipeline: pending, approved and under-construction capacity.

How Malvern Hills decides solar, wind and battery applications

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Malvern Hills

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.