Whitehouse Farm Energy Barn (40 MW battery storage)

Whitehouse Farm Energy Barn is a 40 MW battery storage project in Malvern Hills, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 November 2017, not yet built; the record was last updated on 30 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
30 June 2020record last updated
Malvern Hillscouncil area

Planning timeline

DateStage
3 October 2017Application submitted
29 November 2017Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
30 June 2020
Operator or applicant
Bluefield Solar Income Fund
Planning authority
Malvern Hills
Planning application reference
17/01504/FUL
Address (REPD)
Whitehouse Farm, Blakes Lane, Guarlford, Malvern,
Council area (by location)
Malvern Hills
Time to decision
8 weeks
REPD reference
7987

Who decides

ApplicationsMalvern HillsUK
Decided applications (solar, wind, battery)1410,236
Refused7 (50%)19%
Solar refused5 of 1012%
Onshore wind refused1 of 245%
Battery storage refused1 of 216%
Median time from submission to decision20.6 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chapel Hill Solar Arrayssolar farm49.9refused5.0
Defford Aerodromesolar farm49.9permission expired7.5
Croome Airfield Solar Farmsolar farm49.9operational7.6
Glebe Farm Solar Farmsolar farm32operational8.8
Home Farmsolar farm25approved, not built8.9
Lower Strensham, Bourne Road (Extension)solar farm8operational8.9
Home Farmsolar farm25approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1089, -2.261).