Lower Strensham, Bourne Road (Extension) (8 MW solar farm)

Lower Strensham, Bourne Road (Extension) is an 8 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2021; the record was last updated on 31 March 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
31 March 2022record last updated
Wychavoncouncil area

Planning timeline

DateStage
25 July 2019Application submitted
23 October 2019Planning permission granted
1 June 2020Construction started
1 January 2021Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
31 March 2022
Operator or applicant
NextEnergy Capital LLP
Planning authority
Wychavon
Planning application reference
19/01680/FUL
Site area
18.6 ha
Address (REPD)
Land North Of Strensham, Bourne Road, Defford, Worcester,
Council area (by location)
Wychavon
Time to decision
13 weeks
REPD reference
7423

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Glebe Farm Solar Farmsolar farm32operational0.5
Croome Airfield Solar Farmsolar farm49.9operational1.9
Defford Aerodromesolar farm49.9permission expired1.9
Home Farmsolar farm25approved, not built2.0
Home Farmsolar farm25approved, not built2.8
Strensham Wind Clusterwind farm6application withdrawn3.1
Northway Lane Waste Transfer Stationbattery storage7abandoned7.9
Whitehouse Farm Energy Barnbattery storage40approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0726, -2.1447).