Solar, wind and battery projects near Pershore (WR10)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WR10 (Wychavon): 12 approved but not yet running, 6 operational. The largest live scheme is Bishampton Solar Farm (30 MW solar farm, under construction), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of WR10
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rotherdale Farmsolar farm | solar farm | 5 | operationalupdated May 2013 | Nov 2012 | granted Jan 2013 | May 2013 | Wychavon | 4.4 |
| Rotherdale Farm - extensionsolar farm | solar farm | 9 | operationalupdated Mar 2017 | Apr 2014 | granted Jun 2014 | Mar 2017 | Wychavon | 4.8 |
| Rotherdale Farm (3rd Phase)solar farm | solar farm | 5 | abandonedupdated Nov 2018 | Mar 2015 | granted Jul 2015 | Nov 2018 | Wychavon | 4.8 |
| Croome Airfield Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Jan 2026 | Dec 2019 | granted Jul 2020 | Jan 2026 | Wychavon | 6.7 |
| Defford Aerodromesolar farm | solar farm | 49.9 | permission expiredupdated Mar 2018 | Jun 2014 | granted Jan 2015 | Mar 2018 | Wychavon | 6.7 |
| Bishampton Solar Farmsolar farm | solar farm | 30 | under constructionupdated Apr 2021 | Oct 2020 | granted Nov 2021 | Apr 2021 | Wychavon | 6.9 |
| Bishampton Solar Farmbattery storage | battery storage | 8.8 | abandonedupdated Dec 2022 | Oct 2020 | — | Dec 2022 | Wychavon | 6.9 |
| Lenchwickwind farm | wind farm | 11.5 | refusedupdated Nov 2015 | May 2010 | refused Jan 2011 | Nov 2015 | Wychavon | 6.9 |
| Lower Strensham, Bourne Road (Extension)solar farm | solar farm | 8 | operationalupdated Mar 2022 | Jul 2019 | granted Oct 2019 | Mar 2022 | Wychavon | 7.1 |
| Mucknell Farm Lane, Stoulton Solar Farmsolar farm | solar farm | 1 | refusedupdated May 2024 | Oct 2022 | refused May 2024 | May 2024 | Wychavon | 7.1 |
| Norton Fields Farmwind turbine | wind turbine | 1.3 | operationalupdated Jun 2016 | Jul 2014 | granted Dec 2014 | Jun 2016 | Wychavon | 7.5 |
| Glebe Farm Solar Farmsolar farm | solar farm | 32 | operationalupdated Sep 2020 | May 2015 | granted Oct 2015 | Sep 2020 | Wychavon | 7.6 |
| Home Farmsolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Jun 2023 | granted May 2025 | Feb 2026 | Wychavon | 9.0 |
| Home Farmsolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Jun 2023 | granted Jun 2025 | Feb 2026 | Wychavon | 9.7 |
| Strensham Wind Clusterwind farm | wind farm | 6 | application withdrawnupdated Aug 2013 | Apr 2011 | — | Aug 2013 | Tewkesbury | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hyde Farm, Worcester Roadsolar farm | solar farm | 0.1 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | Wychavon | 2.7 |
| Bishampton Solar Energy Park, Broad Lanebattery storage | battery storage | — | approved, not builtupdated Dec 2025 | May 2025 | granted Nov 2025 | Dec 2025 | Wychavon | 6.2 |
| Lower Strenshambattery storage | battery storage | — | approved, not built may be out of dateupdated Aug 2022 | Jul 2022 | granted Sep 2022 | Aug 2022 | Wychavon | 7.4 |
| Woodbury Lane, Nortonrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Apr 2024 | Apr 2024 | Wychavon | 7.9 |
| Holdsworth Distribution Centre, Hinton On The Greenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Jun 2023 | granted Nov 2023 | Nov 2023 | Wychavon | 8.6 |
| Evesham Garden Centre, Evesham Country Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Jan 2023 | granted Apr 2023 | May 2023 | Wychavon | 8.9 |
| Home Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Jun 2023 | granted May 2025 | Feb 2026 | Wychavon | 9.0 |
| Home Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Jun 2023 | granted Jun 2025 | Feb 2026 | Wychavon | 9.0 |
| Fircone Farm, Church Road - 249KW Solar Panelssolar farm | solar farm | 0.2 | application withdrawnupdated Jun 2026 | Apr 2025 | — | Jun 2026 | Wychavon | 9.6 |
| Bramley Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | May 2022 | granted Jun 2022 | May 2022 | Wychavon | 9.9 |
Distance from the average position of the WR10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 0 | 4 | 5 | 1 | 80.2 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 0.8 |
| Wind farm | 2 | 0 | 0 | 0 | 1 | 0 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 5 | 0 | 4 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Wychavon decides solar, wind and battery applications
| Applications | Wychavon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 50 | 10,236 |
| Refused | 3 (6%) | 19% |
| Solar refused | 2 of 34 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 0 of 14 | 16% |
| Median time from submission to decision | 20.5 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near WR10, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.