Solar, wind and battery projects near Tewkesbury (GL20)
25 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL20 (Tewkesbury): 11 approved but not yet running, 7 operational. The largest live scheme is Claydon Farm Solar Farm & Battery Storage (49.9 MW solar farm, approved on 17 December 2021, not yet built), 3.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of GL20
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Northway Lane Waste Transfer Stationbattery storage | battery storage | 7 | abandonedupdated Jan 2019 | Jan 2017 | — | Jan 2019 | Tewkesbury | 0.1 |
| Walton Cardiff Manorsolar farm | solar farm | 2 | refusedupdated Oct 2015 | Aug 2015 | refused Dec 2015 | Oct 2015 | Tewkesbury | 1.5 |
| Claydon Farm Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Dec 2021 | Jan 2021 | granted Dec 2021 | Dec 2021 | Tewkesbury | 3.1 |
| Claydon Farm Solar Farm & Battery Storagebattery storage | battery storage | 49.9 | approved, not builtupdated Feb 2021 | Jan 2021 | granted Dec 2021 | Feb 2021 | Tewkesbury | 3.1 |
| Claydon Farmsolar farm | solar farm | 18.2 | abandonedupdated Feb 2016 | Sep 2014 | granted Feb 2015 | Feb 2016 | Tewkesbury | 3.9 |
| Tredington House Farm, Tredingtonbattery storage | battery storage | 40 | approved, not builtupdated Jan 2025 | May 2024 | granted Dec 2024 | Jan 2025 | Tewkesbury | 4.6 |
| Troughton Farmsolar farm | solar farm | 30 | operationalupdated Jul 2016 | Feb 2013 | granted Jul 2014 | Jul 2016 | Tewkesbury | 4.8 |
| Strensham Wind Clusterwind farm | wind farm | 6 | application withdrawnupdated Aug 2013 | Apr 2011 | — | Aug 2013 | Tewkesbury | 5.0 |
| Land to the North of Cursey Lanesolar farm | solar farm | 4 | permission expiredupdated Jul 2020 | Jul 2015 | granted Nov 2016 | Jul 2020 | Tewkesbury | 5.6 |
| Home Farmsolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Jun 2023 | granted Jun 2025 | Feb 2026 | Wychavon | 5.7 |
| Home Farmsolar farm | solar farm | 25 | approved, not builtupdated Feb 2026 | Jun 2023 | granted May 2025 | Feb 2026 | Wychavon | 6.6 |
| Glebe Farm Solar Farmsolar farm | solar farm | 32 | operationalupdated Sep 2020 | May 2015 | granted Oct 2015 | Sep 2020 | Wychavon | 7.6 |
| Home Farmsolar farm | solar farm | 6.7 | operationalupdated Jun 2017 | Mar 2015 | granted Oct 2015 | Jun 2017 | Tewkesbury | 7.9 |
| Lower Strensham, Bourne Road (Extension)solar farm | solar farm | 8 | operationalupdated Mar 2022 | Jul 2019 | granted Oct 2019 | Mar 2022 | Wychavon | 7.9 |
| Lower Stanley Farmsolar farm | solar farm | 4 | operationalupdated Feb 2017 | Apr 2015 | granted Sep 2015 | Feb 2017 | Tewkesbury | 9.4 |
| Hayden Hill Fruit Farmsolar farm | solar farm | 5 | refusedupdated May 2016 | Sep 2015 | refused Apr 2016 | May 2016 | Tewkesbury | 9.6 |
| Croome Airfield Solar Farmsolar farm | solar farm | 49.9 | operationalupdated Jan 2026 | Dec 2019 | granted Jul 2020 | Jan 2026 | Wychavon | 9.8 |
| Defford Aerodromesolar farm | solar farm | 49.9 | permission expiredupdated Mar 2018 | Jun 2014 | granted Jan 2015 | Mar 2018 | Wychavon | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Dairy Way, Northway Lane, Unit 22rooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Tewkesbury | 0.6 |
| Moog Controls Factoryrooftop solar | rooftop solar | 0.4 | operationalupdated Feb 2024 | Nov 2018 | granted Jan 2021 | Feb 2024 | Tewkesbury | 1.4 |
| Gloucester Road Solar Carport Arraysolar farm | solar farm | 0.2 | approved, not builtupdated Jan 2022 | Jan 2022 | granted Mar 2022 | Jan 2022 | Tewkesbury | 2.9 |
| Home Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Jun 2023 | granted Jun 2025 | Feb 2026 | Wychavon | 6.6 |
| Home Farmbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Jun 2023 | granted May 2025 | Feb 2026 | Wychavon | 6.6 |
| Lower Strenshambattery storage | battery storage | — | approved, not built may be out of dateupdated Aug 2022 | Jul 2022 | granted Sep 2022 | Aug 2022 | Wychavon | 7.3 |
| All Saints Academy, Blaisdon Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Nov 2025 | Dec 2025 | Cheltenham | 9.8 |
Distance from the average position of the GL20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 0 | 4 | 6 | 2 | 100 |
| Rooftop solar | 3 | 0 | 2 | 1 | 0 | 0.8 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 6 | 0 | 5 | 0 | 0 | 89.9 |
MW in pipeline: pending, approved and under-construction capacity.
How Tewkesbury decides solar, wind and battery applications
| Applications | Tewkesbury | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 31 | 10,236 |
| Refused | 5 (16%) | 19% |
| Solar refused | 5 of 27 | 12% |
| Battery storage refused | 0 of 4 | 16% |
| Median time from submission to decision | 25.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 3 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL20, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.