Energy Projects Near You

Solar, wind and battery projects near Gloucester (GL19)

34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL19 (Forest of Dean): 7 are waiting for a planning decision, 18 approved but not yet running, 5 operational. The largest live scheme is Linton Court Farm, Highnam (99.9 MW battery storage, approved on 21 August 2023, not yet built), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34projects within 10 km
7awaiting a decision
18approved, not running
5operational

Projects within 10 km of GL19

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Stream Lane, Upleadon Solar Photovoltaic Farmsolar farmsolar farm6refusedupdated Aug 2023Oct 2022refused Jul 2023Aug 2023Forest of Dean5.1
Murrells End Farm Solar Arrayssolar farmsolar farm49.9refusedupdated Jun 2022Jun 2022refused Mar 2023Jun 2022Forest of Dean5.2
Bengrove Farm, Base Lanebattery storagebattery storage49.9application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022Tewkesbury5.5
Bengrove Farm, Base Lane Solar Farmsolar farmsolar farm15approved, not builtupdated Sep 2025Jan 2024granted Oct 2024Sep 2025Tewkesbury5.5
Highleadon Solar Arrays & Battery Storagesolar farmsolar farm49.9operationalupdated Apr 2026Feb 2022granted Oct 2023Apr 2026Forest of Dean5.7
Land At Rymes Farm (Phase 1)solar farmsolar farm6.9operationalupdated Jul 2016Dec 2014granted Jun 2015Jul 2016Forest of Dean6.4
Land At Rymes Farm (Phase 2)/Grange Solar Farmsolar farmsolar farm6.8operationalupdated Sep 2016Dec 2014granted Jun 2015Sep 2016Forest of Dean6.5
Maisemore Solar Farmsolar farmsolar farm37approved, not built may be out of dateupdated Jun 2023Apr 2022granted Mar 2023Jun 2023Tewkesbury6.5
Lassington Lane, Highnam Solar Farmsolar farmsolar farm40application submittedupdated Sep 2025Jul 2025—Sep 2025Tewkesbury6.8
Lassington Lane, Highnambattery storagebattery storage10application submittedupdated Sep 2025Jul 2025—Sep 2025Tewkesbury6.8
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farmsolar farm16approved, not builtupdated Feb 2026May 2023granted Apr 2024Feb 2026Tewkesbury6.9
Moat Farm Solar Farmsolar farmsolar farm49.9approved, not builtupdated Jun 2026Jan 2022granted May 2026Jun 2026Forest of Dean7.5
Highnam Solar Farmsolar farmsolar farm5abandonedupdated Nov 2019Jun 2015granted Jun 2016Nov 2019Tewkesbury7.6
Two Mile Lane, Highnam Solar Farmsolar farmsolar farm36application submittedupdated May 2026Mar 2026—May 2026Tewkesbury7.9
Over Farmsolar farmsolar farm9.9approved, not built may be out of dateupdated Nov 2019May 2015granted Jun 2016Nov 2019Tewkesbury8.0
Linton Court Farm, Highnambattery storagebattery storage99.9approved, not builtupdated Sep 2023Dec 2022granted Aug 2023Sep 2023Tewkesbury8.4
Hempsted Lanesolar farmsolar farm2approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022Gloucester9.3
Registry Twyver House, Bruton Wayrooftop solarrooftop solar8.8application withdrawnupdated Mar 2023Feb 2023—Mar 2023Gloucester9.6
Sudmeadow Road, Hempstedbattery storagebattery storage50approved, not builtupdated Jan 2026Oct 2024granted Nov 2025Jan 2026Gloucester9.6
Meteor Business Parkbattery storagebattery storage1.5operationalupdated Jan 2020Feb 2019—Jan 2020Tewkesbury9.7
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Farm Consultancy Grouprooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Tewkesbury5.1
Grove Farm - Microgrid of Solar Panelssolar farmsolar farm—application submittedupdated Sep 2025Aug 2025—Sep 2025Malvern Hills5.6
Highleadon Solar Arrays & Battery Storagebattery storagebattery storage—operationalupdated Apr 2026Feb 2022granted Oct 2023Apr 2026Forest of Dean5.7
Hatherley Manor Hotel, Down Hatherley Lanerooftop solarrooftop solar0.2application submitted may be out of dateupdated Sep 2022Aug 2022—Sep 2022Tewkesbury7.4
Oxstalls Tennis Centrerooftop solarrooftop solar0.3approved, not builtupdated Sep 2021Mar 2021granted Apr 2021Sep 2021Gloucester8.2
Millers Court Farm, Birts Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Malvern Hills9.1
Quayside Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Sep 2021Jan 2021granted May 2021Sep 2021Gloucester9.2
Safran Landing System, Down Hatherley Lanerooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Tewkesbury9.3
Gloucester Royal Hospitalbattery storagebattery storage—approved, not builtupdated Dec 2021Aug 2021granted Sep 2021Dec 2021Gloucester9.5
Gloucestershire College - Photovoltaic Solar Panelsrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Aug 2021granted May 2022Nov 2021Gloucester9.6
Gloucester Royal Hospitalrooftop solarrooftop solar0.2approved, not builtupdated Jun 2021May 2021granted Jul 2021Jun 2021Gloucester9.6
Gloucester Road Solar Carport Arraysolar farmsolar farm0.2approved, not builtupdated Jan 2022Jan 2022granted Mar 2022Jan 2022Tewkesbury9.7
Bruton Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Gloucester9.8
Motus Commercials, Spinnaker Roadrooftop solarrooftop solar0.3application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Gloucester9.8

Distance from the average position of the GL19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm163732206
Rooftop solar1128002.2
Battery storage72320210

MW in pipeline: pending, approved and under-construction capacity.

How Forest of Dean decides solar, wind and battery applications

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

All projects in Forest of Dean

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL19, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.