Energy Projects Near You

Stream Lane, Upleadon Solar Photovoltaic Farm (6 MW)

Stream Lane, Upleadon Solar Photovoltaic Farm is a 6 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 July 2023; the record was last updated on 4 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
refusedstatus in REPD
4 August 2023record last updated
Forest of Deancouncil area

Planning timeline

DateStage
5 October 2022Application submitted
12 July 2023Refused by the planning authority

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
refused
Record last updated
4 August 2023
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Forest of Dean
Planning application reference
P1350/22/FUL
Site area
13.7 ha
Address (REPD)
N/O Stream Lane, Upleadon, Dymock
Council area (by location)
Forest of Dean
Time to decision
40 weeks
Name in REPD
Stream Lane, Upleadon - Solar Photovoltaic Farm
REPD reference
12359

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Rymes Farm (Phase 2)/Grange Solar Farmsolar farm6.8operational1.9
Land At Rymes Farm (Phase 1)solar farm6.9operational2.0
Moat Farm Solar Farmsolar farm49.9approved, not built2.6
Highleadon Solar Arrays & Battery Storagesolar farm49.9operational3.2
Murrells End Farm Solar Arrayssolar farm49.9refused5.4
Lassington Lane, Highnam Solar Farmsolar farm40application submitted7.1
Lassington Lane, Highnambattery storage10application submitted7.1
Highnam Solar Farmsolar farm5abandoned7.4
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.935, -2.3617).