Stream Lane, Upleadon Solar Photovoltaic Farm (6 MW)
Stream Lane, Upleadon Solar Photovoltaic Farm is a 6 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 July 2023; the record was last updated on 4 August 2023.
6 MWsolar farm
refusedstatus in REPD
4 August 2023record last updated
Forest of Deancouncil area
Planning timeline
| Date | Stage |
|---|---|
| 5 October 2022 | Application submitted |
| 12 July 2023 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 6 MW
- Status (REPD)
- refused
- Record last updated
- 4 August 2023
- Operator or applicant
- Pathfinder Clean Energy UK Dev Limited
- Planning authority
- Forest of Dean
- Planning application reference
- P1350/22/FUL
- Site area
- 13.7 ha
- Address (REPD)
- N/O Stream Lane, Upleadon, Dymock
- Council area (by location)
- Forest of Dean
- Time to decision
- 40 weeks
- Name in REPD
- Stream Lane, Upleadon - Solar Photovoltaic Farm
- REPD reference
- 12359
Who decides
| Applications | Forest of Dean | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 28 | 10,236 |
| Refused | 8 (29%) | 19% |
| Solar refused | 7 of 26 | 12% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 14.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 1 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Land At Rymes Farm (Phase 2)/Grange Solar Farm | solar farm | 6.8 | operational | 1.9 |
| Land At Rymes Farm (Phase 1) | solar farm | 6.9 | operational | 2.0 |
| Moat Farm Solar Farm | solar farm | 49.9 | approved, not built | 2.6 |
| Highleadon Solar Arrays & Battery Storage | solar farm | 49.9 | operational | 3.2 |
| Murrells End Farm Solar Arrays | solar farm | 49.9 | refused | 5.4 |
| Lassington Lane, Highnam Solar Farm | solar farm | 40 | application submitted | 7.1 |
| Lassington Lane, Highnam | battery storage | 10 | application submitted | 7.1 |
| Highnam Solar Farm | solar farm | 5 | abandoned | 7.4 |
| Two Mile Lane, Highnam Solar Farm | solar farm | 36 | application submitted | 7.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.935, -2.3617).