Highleadon Solar Arrays & Battery Storage (49.9 MW)

Highleadon Solar Arrays & Battery Storage is a 49.9 MW solar farm project in Forest of Dean, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2025; the record was last updated on 24 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
operationalstatus in REPD
24 April 2026record last updated
Forest of Deancouncil area

Planning timeline

DateStage
16 February 2022Application submitted
11 October 2023Planning permission granted
1 December 2025Operational

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
24 April 2026
Operator or applicant
RWE
Planning authority
Forest of Dean
Planning application reference
P0265/22/FUL
Site area
116.0 ha
Address (REPD)
Near Highleadon Highleadon
Council area (by location)
Forest of Dean
Time to decision
86 weeks
Contracts for Difference
AR6
Name in REPD
Highleadon - Solar Arrays & Battery Storage
REPD reference
10797

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsForest of DeanUK
Decided applications (solar, wind, battery)2810,236
Refused8 (29%)19%
Solar refused7 of 2612%
Battery storage refused1 of 216%
Median time from submission to decision14.1 weeks17.0 weeks
Appeals lodged / allowed2 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Rymes Farm (Phase 1)solar farm6.9operational2.2
Land At Rymes Farm (Phase 2)/Grange Solar Farmsolar farm6.8operational2.4
Murrells End Farm Solar Arrayssolar farm49.9refused2.7
Moat Farm Solar Farmsolar farm49.9approved, not built3.2
Stream Lane, Upleadon Solar Photovoltaic Farmsolar farm6refused3.2
Lassington Lane, Highnam Solar Farmsolar farm40application submitted4.1
Lassington Lane, Highnambattery storage10application submitted4.1
Highnam Solar Farmsolar farm5abandoned4.2
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9077, -2.3452).