Lassington Lane, Highnam (10 MW battery storage)

Lassington Lane, Highnam is a 10 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 11 July 2025, no decision recorded; the record was last updated on 1 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWbattery storage
application submittedstatus in REPD
1 September 2025record last updated
Tewkesburycouncil area

Planning timeline

DateStage
11 July 2025Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
10 MW
Status (REPD)
application submitted
Record last updated
1 September 2025
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Tewkesbury
Planning application reference
25/00566/FUL
Address (REPD)
Part Parcel 8900, Lassington Lane, Highnam, Gloucester
Council area (by location)
Tewkesbury
Name in REPD
Lassington Lane, Highnam - Battery Storage
REPD reference
19390

Recorded together with Lassington Lane, Highnam Solar Farm (40 MW solar farm, application submitted).

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highnam Solar Farmsolar farm5abandoned0.9
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted1.2
Maisemore Solar Farmsolar farm37approved, not built1.4
Linton Court Farm, Highnambattery storage99.9approved, not built1.7
Murrells End Farm Solar Arrayssolar farm49.9refused1.8
Over Farmsolar farm9.9approved, not built2.0
Sudmeadow Road, Hempstedbattery storage50approved, not built3.7
Highleadon Solar Arrays & Battery Storagesolar farm49.9operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8842, -2.2992).