Linton Court Farm, Highnam (99.9 MW battery storage)

Linton Court Farm, Highnam is a 99.9 MW battery storage project in Tewkesbury, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 August 2023, not yet built; the record was last updated on 8 September 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtstatus in REPD
8 September 2023record last updated
Tewkesburycouncil area

Planning timeline

DateStage
20 December 2022Application submitted
21 August 2023Planning permission granted
21 August 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
8 September 2023
Operator or applicant
STOR 136 Limited
Planning authority
Tewkesbury
Planning application reference
22/01374/FUL
Address (REPD)
Linton Court Farm, Highnam
Council area (by location)
Tewkesbury
Time to decision
35 weeks
Name in REPD
Linton Court Farm, Highnam - Battery storage
REPD reference
13145

Who decides

ApplicationsTewkesburyUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2712%
Battery storage refused0 of 416%
Median time from submission to decision25.0 weeks17.0 weeks
Appeals lodged / allowed3 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Over Farmsolar farm9.9approved, not built1.1
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted1.5
Highnam Solar Farmsolar farm5abandoned1.5
Lassington Lane, Highnam Solar Farmsolar farm40application submitted1.7
Lassington Lane, Highnambattery storage10application submitted1.7
Maisemore Solar Farmsolar farm37approved, not built2.0
Sudmeadow Road, Hempstedbattery storage50approved, not built2.2
Registry Twyver House, Bruton Wayrooftop solar8.8application withdrawn3.4
Bristol Roadbattery storage20permission expired3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8702, -2.2887).