Energy Projects Near You

Bristol Road (20 MW battery storage)

Bristol Road is a 20 MW battery storage project in Gloucester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired; the record was last updated on 28 April 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
permission expiredstatus in REPD
28 April 2020record last updated
Gloucestercouncil area

Planning timeline

DateStage
30 August 2016Application submitted

Project details

Technology
battery storage (co-located with fossil fuel plant)
Capacity
20 MW
Status (REPD)
permission expired
Record last updated
28 April 2020
Operator or applicant
UK Power Reserve
Planning authority
Gloucester
Planning application reference
16/01044/FUL
Address (REPD)
NGPlot 6 Bristol Road Gloucester
Council area (by location)
Gloucester
REPD reference
6930

Who decides

ApplicationsGloucesterUK
Decided applications (solar, wind, battery)1910,236
Refused1 (5%)19%
Solar refused1 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sudmeadow Road, Hempstedbattery storage50approved, not built2.1
Brookthorpe Solar Farmsolar farm8approved, not built2.4
Registry Twyver House, Bruton Wayrooftop solar8.8application withdrawn3.1
Linton Court Farm, Highnambattery storage99.9approved, not built3.5
Over Farmsolar farm9.9approved, not built3.6
Two Mile Lane, Highnam Solar Farmsolar farm36application submitted4.7
Highnam Solar Farmsolar farm5abandoned4.9
Maisemore Solar Farmsolar farm37approved, not built5.1
Lassington Lane, Highnam Solar Farmsolar farm40application submitted5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8421, -2.2652).