Energy Projects Near You

Solar, wind and battery projects near Gloucester (GL1)

59 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL1 (Gloucester): 6 are waiting for a planning decision, 39 approved but not yet running, 5 operational. The largest live scheme is Linton Court Farm, Highnam (99.9 MW battery storage, approved on 21 August 2023, not yet built), 3.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

59projects within 10 km
6awaiting a decision
39approved, not running
5operational

Projects within 10 km of GL1

Projects of 1 MW and more (29)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Registry Twyver House, Bruton Wayrooftop solarrooftop solar8.8application withdrawnupdated Mar 2023Feb 2023—Mar 2023Gloucester0.7
Sudmeadow Road, Hempstedbattery storagebattery storage50approved, not builtupdated Jan 2026Oct 2024granted Nov 2025Jan 2026Gloucester1.1
Hempsted Lanesolar farmsolar farm2approved, not builtupdated May 2022Apr 2022granted Aug 2023May 2022Gloucester1.7
Bristol Roadbattery storagebattery storage20permission expiredupdated Apr 2020Aug 2016—Apr 2020Gloucester2.4
Over Farmsolar farmsolar farm9.9approved, not built may be out of dateupdated Nov 2019May 2015granted Jun 2016Nov 2019Tewkesbury2.7
Unilever UK, Corinium Avenuerooftop solarrooftop solar3.5approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Gloucester3.1
Linton Court Farm, Highnambattery storagebattery storage99.9approved, not builtupdated Sep 2023Dec 2022granted Aug 2023Sep 2023Tewkesbury3.3
Brookthorpe Solar Farmsolar farmsolar farm8approved, not builtupdated Feb 2026Apr 2024granted Dec 2024Feb 2026Stroud3.8
Maisemore Solar Farmsolar farmsolar farm37approved, not built may be out of dateupdated Jun 2023Apr 2022granted Mar 2023Jun 2023Tewkesbury3.9
Solar Array at W/O Twigworth And E/O Coxs Brooksolar farmsolar farm16approved, not builtupdated Feb 2026May 2023granted Apr 2024Feb 2026Tewkesbury4.1
Lassington Lane, Highnam Solar Farmsolar farmsolar farm40application submittedupdated Sep 2025Jul 2025—Sep 2025Tewkesbury4.7
Lassington Lane, Highnambattery storagebattery storage10application submittedupdated Sep 2025Jul 2025—Sep 2025Tewkesbury4.7
Two Mile Lane, Highnam Solar Farmsolar farmsolar farm36application submittedupdated May 2026Mar 2026—May 2026Tewkesbury4.8
Highnam Solar Farmsolar farmsolar farm5abandonedupdated Nov 2019Jun 2015granted Jun 2016Nov 2019Tewkesbury4.8
Bengrove Farm, Base Lanebattery storagebattery storage49.9application submitted may be out of dateupdated Dec 2022Nov 2022—Dec 2022Tewkesbury4.9
Bengrove Farm, Base Lane Solar Farmsolar farmsolar farm15approved, not builtupdated Sep 2025Jan 2024granted Oct 2024Sep 2025Tewkesbury4.9
Plant 1, G-Tekt Europe Manufacturing Limited -Roof Mounted Solar Panelsrooftop solarrooftop solar1under constructionupdated Jul 2022Jun 2022granted Dec 2022Jul 2022Tewkesbury5.3
Plant 4, Hurricane Road, Gloucester Business Parkrooftop solarrooftop solar1approved, not builtupdated Jul 2022Jun 2022granted Sep 2022Jul 2022Tewkesbury5.5
Brockworth Roadbattery storagebattery storage20approved, not builtupdated May 2024Nov 2023granted Apr 2024May 2024Tewkesbury5.9
Unit Q1, Quadrant Distribution Centre, Hardwickrooftop solarrooftop solar1approved, not builtupdated May 2022Apr 2022granted May 2022May 2022Stroud6.0
Murrells End Farm Solar Arrayssolar farmsolar farm49.9refusedupdated Jun 2022Jun 2022refused Mar 2023Jun 2022Forest of Dean6.3
Meteor Business Parkbattery storagebattery storage1.5operationalupdated Jan 2020Feb 2019—Jan 2020Tewkesbury6.5
High Green Longney Estate Solar Farmsolar farmsolar farm25permission expiredupdated Sep 2020Mar 2018granted Sep 2019Sep 2020Stroud8.1
High Green Longney Estate Solar Farmsolar farmsolar farm20permission expiredupdated Jul 2022Apr 2019granted Jul 2019Jul 2022Stroud8.1
Moreton Lane Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud8.6
Moreton Lane Solar Farm & Battery Storagebattery storagebattery storage49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud8.6
Highleadon Solar Arrays & Battery Storagesolar farmsolar farm49.9operationalupdated Apr 2026Feb 2022granted Oct 2023Apr 2026Forest of Dean8.8
Hayden Hill Fruit Farmsolar farmsolar farm5refusedupdated May 2016Sep 2015refused Apr 2016May 2016Tewkesbury9.6
Epney, Framilode Solar Farm & Battery Storagesolar farmsolar farm49.5refusedupdated Dec 2025Jun 2025refused Dec 2025Dec 2025Stroud9.8
Smaller schemes under 1 MW, mostly rooftop solar (30)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bruton Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Gloucester0.5
The Shirt Factoryrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025Gloucester0.8
Gloucestershire College - Photovoltaic Solar Panelsrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Aug 2021granted May 2022Nov 2021Gloucester0.9
Quayside Houserooftop solarrooftop solar—approved, not built may be out of dateupdated Sep 2021Jan 2021granted May 2021Sep 2021Gloucester0.9
Gloucester Royal Hospitalbattery storagebattery storage—approved, not builtupdated Dec 2021Aug 2021granted Sep 2021Dec 2021Gloucester1.0
Gloucester Royal Hospitalrooftop solarrooftop solar0.2approved, not builtupdated Jun 2021May 2021granted Jul 2021Jun 2021Gloucester1.1
Motus Commercials, Spinnaker Roadrooftop solarrooftop solar0.3application submitted may be out of dateupdated Jul 2023Jul 2023—Jul 2023Gloucester1.3
Gloucester Academyrooftop solarrooftop solar0.2approved, not builtupdated May 2022Jun 2020granted May 2021May 2022Gloucester2.2
Oxstalls Tennis Centrerooftop solarrooftop solar0.3approved, not builtupdated Sep 2021Mar 2021granted Apr 2021Sep 2021Gloucester2.6
Sainsburys Supermarketrooftop solarrooftop solar0.6approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Gloucester2.9
Unilever UKrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Gloucester3.1
Morrisons Supermarket, Glevum Wayrooftop solarrooftop solar—approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Gloucester3.3
Tenpin Centre, Severn Barnwood Link Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Gloucester3.3
Arlingham House, Quedgeleyrooftop solarrooftop solar0.3approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Gloucester3.7
Mobile Telephone Exchange (MTX)rooftop solarrooftop solar—operationalupdated Apr 2023Dec 2022—Apr 2023Gloucester3.8
David Lloyd Leisure, Whittle Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Tewkesbury5.1
Laithwaites Wines, Gloucester Business Parkrooftop solarrooftop solar0.8approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Tewkesbury5.4
Tbs Engineering, Gloucester Business Parkrooftop solarrooftop solar0.5approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Tewkesbury5.4
The Farm Consultancy Grouprooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025Tewkesbury5.4
Francis And Lewis International, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Gloucester5.5
Alpha Colour Printers, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Gloucester5.5
Hatherley Manor Hotel, Down Hatherley Lanerooftop solarrooftop solar0.2application submitted may be out of dateupdated Sep 2022Aug 2022—Sep 2022Tewkesbury5.5
The Io Centre, Gloucester Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Tewkesbury5.5
The IO Centre, Gloucester Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024Tewkesbury5.5
MG Markey Group, Quadrant Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Stroud6.0
Safran Landing System, Down Hatherley Lanerooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Tewkesbury6.3
Anson Business Park, Cheltenham Road Eastrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Tewkesbury7.0
Dobbies Garden Centres, Bath Roadrooftop solarrooftop solar0.2application withdrawnupdated Dec 2023Oct 2023—Dec 2023Stroud8.1
Leewayssolar farmsolar farm0.5operationalupdated Nov 2019Oct 2018granted Jan 2019Nov 2019Forest of Dean8.6
Highleadon Solar Arrays & Battery Storagebattery storagebattery storage—operationalupdated Apr 2026Feb 2022granted Oct 2023Apr 2026Forest of Dean8.8

Distance from the average position of the GL1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm172723214
Rooftop solar322271013.1
Battery storage102520280

MW in pipeline: pending, approved and under-construction capacity.

How Gloucester decides solar, wind and battery applications

ApplicationsGloucesterUK
Decided applications (solar, wind, battery)1910,236
Refused1 (5%)19%
Solar refused1 of 1712%
Battery storage refused0 of 216%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Gloucester

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL1, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.