Solar, wind and battery projects near Gloucester (GL1)
59 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL1 (Gloucester): 6 are waiting for a planning decision, 39 approved but not yet running, 5 operational. The largest live scheme is Linton Court Farm, Highnam (99.9 MW battery storage, approved on 21 August 2023, not yet built), 3.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of GL1
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Registry Twyver House, Bruton Wayrooftop solar | rooftop solar | 8.8 | application withdrawnupdated Mar 2023 | Feb 2023 | — | Mar 2023 | Gloucester | 0.7 |
| Sudmeadow Road, Hempstedbattery storage | battery storage | 50 | approved, not builtupdated Jan 2026 | Oct 2024 | granted Nov 2025 | Jan 2026 | Gloucester | 1.1 |
| Hempsted Lanesolar farm | solar farm | 2 | approved, not builtupdated May 2022 | Apr 2022 | granted Aug 2023 | May 2022 | Gloucester | 1.7 |
| Bristol Roadbattery storage | battery storage | 20 | permission expiredupdated Apr 2020 | Aug 2016 | — | Apr 2020 | Gloucester | 2.4 |
| Over Farmsolar farm | solar farm | 9.9 | approved, not built may be out of dateupdated Nov 2019 | May 2015 | granted Jun 2016 | Nov 2019 | Tewkesbury | 2.7 |
| Unilever UK, Corinium Avenuerooftop solar | rooftop solar | 3.5 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | Gloucester | 3.1 |
| Linton Court Farm, Highnambattery storage | battery storage | 99.9 | approved, not builtupdated Sep 2023 | Dec 2022 | granted Aug 2023 | Sep 2023 | Tewkesbury | 3.3 |
| Brookthorpe Solar Farmsolar farm | solar farm | 8 | approved, not builtupdated Feb 2026 | Apr 2024 | granted Dec 2024 | Feb 2026 | Stroud | 3.8 |
| Maisemore Solar Farmsolar farm | solar farm | 37 | approved, not built may be out of dateupdated Jun 2023 | Apr 2022 | granted Mar 2023 | Jun 2023 | Tewkesbury | 3.9 |
| Solar Array at W/O Twigworth And E/O Coxs Brooksolar farm | solar farm | 16 | approved, not builtupdated Feb 2026 | May 2023 | granted Apr 2024 | Feb 2026 | Tewkesbury | 4.1 |
| Lassington Lane, Highnam Solar Farmsolar farm | solar farm | 40 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Tewkesbury | 4.7 |
| Lassington Lane, Highnambattery storage | battery storage | 10 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Tewkesbury | 4.7 |
| Two Mile Lane, Highnam Solar Farmsolar farm | solar farm | 36 | application submittedupdated May 2026 | Mar 2026 | — | May 2026 | Tewkesbury | 4.8 |
| Highnam Solar Farmsolar farm | solar farm | 5 | abandonedupdated Nov 2019 | Jun 2015 | granted Jun 2016 | Nov 2019 | Tewkesbury | 4.8 |
| Bengrove Farm, Base Lanebattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Dec 2022 | Nov 2022 | — | Dec 2022 | Tewkesbury | 4.9 |
| Bengrove Farm, Base Lane Solar Farmsolar farm | solar farm | 15 | approved, not builtupdated Sep 2025 | Jan 2024 | granted Oct 2024 | Sep 2025 | Tewkesbury | 4.9 |
| Plant 1, G-Tekt Europe Manufacturing Limited -Roof Mounted Solar Panelsrooftop solar | rooftop solar | 1 | under constructionupdated Jul 2022 | Jun 2022 | granted Dec 2022 | Jul 2022 | Tewkesbury | 5.3 |
| Plant 4, Hurricane Road, Gloucester Business Parkrooftop solar | rooftop solar | 1 | approved, not builtupdated Jul 2022 | Jun 2022 | granted Sep 2022 | Jul 2022 | Tewkesbury | 5.5 |
| Brockworth Roadbattery storage | battery storage | 20 | approved, not builtupdated May 2024 | Nov 2023 | granted Apr 2024 | May 2024 | Tewkesbury | 5.9 |
| Unit Q1, Quadrant Distribution Centre, Hardwickrooftop solar | rooftop solar | 1 | approved, not builtupdated May 2022 | Apr 2022 | granted May 2022 | May 2022 | Stroud | 6.0 |
| Murrells End Farm Solar Arrayssolar farm | solar farm | 49.9 | refusedupdated Jun 2022 | Jun 2022 | refused Mar 2023 | Jun 2022 | Forest of Dean | 6.3 |
| Meteor Business Parkbattery storage | battery storage | 1.5 | operationalupdated Jan 2020 | Feb 2019 | — | Jan 2020 | Tewkesbury | 6.5 |
| High Green Longney Estate Solar Farmsolar farm | solar farm | 25 | permission expiredupdated Sep 2020 | Mar 2018 | granted Sep 2019 | Sep 2020 | Stroud | 8.1 |
| High Green Longney Estate Solar Farmsolar farm | solar farm | 20 | permission expiredupdated Jul 2022 | Apr 2019 | granted Jul 2019 | Jul 2022 | Stroud | 8.1 |
| Moreton Lane Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Apr 2022 | Feb 2021 | granted Apr 2022 | Apr 2022 | Stroud | 8.6 |
| Moreton Lane Solar Farm & Battery Storagebattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Apr 2022 | Feb 2021 | granted Apr 2022 | Apr 2022 | Stroud | 8.6 |
| Highleadon Solar Arrays & Battery Storagesolar farm | solar farm | 49.9 | operationalupdated Apr 2026 | Feb 2022 | granted Oct 2023 | Apr 2026 | Forest of Dean | 8.8 |
| Hayden Hill Fruit Farmsolar farm | solar farm | 5 | refusedupdated May 2016 | Sep 2015 | refused Apr 2016 | May 2016 | Tewkesbury | 9.6 |
| Epney, Framilode Solar Farm & Battery Storagesolar farm | solar farm | 49.5 | refusedupdated Dec 2025 | Jun 2025 | refused Dec 2025 | Dec 2025 | Stroud | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bruton Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Gloucester | 0.5 |
| The Shirt Factoryrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jun 2025 | Jul 2025 | Gloucester | 0.8 |
| Gloucestershire College - Photovoltaic Solar Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2021 | Aug 2021 | granted May 2022 | Nov 2021 | Gloucester | 0.9 |
| Quayside Houserooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Sep 2021 | Jan 2021 | granted May 2021 | Sep 2021 | Gloucester | 0.9 |
| Gloucester Royal Hospitalbattery storage | battery storage | — | approved, not builtupdated Dec 2021 | Aug 2021 | granted Sep 2021 | Dec 2021 | Gloucester | 1.0 |
| Gloucester Royal Hospitalrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2021 | May 2021 | granted Jul 2021 | Jun 2021 | Gloucester | 1.1 |
| Motus Commercials, Spinnaker Roadrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Gloucester | 1.3 |
| Gloucester Academyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2022 | Jun 2020 | granted May 2021 | May 2022 | Gloucester | 2.2 |
| Oxstalls Tennis Centrerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2021 | Mar 2021 | granted Apr 2021 | Sep 2021 | Gloucester | 2.6 |
| Sainsburys Supermarketrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Jan 2026 | Mar 2026 | Gloucester | 2.9 |
| Unilever UKrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Gloucester | 3.1 |
| Morrisons Supermarket, Glevum Wayrooftop solar | rooftop solar | — | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Gloucester | 3.3 |
| Tenpin Centre, Severn Barnwood Link Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | Gloucester | 3.3 |
| Arlingham House, Quedgeleyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | Gloucester | 3.7 |
| Mobile Telephone Exchange (MTX)rooftop solar | rooftop solar | — | operationalupdated Apr 2023 | Dec 2022 | — | Apr 2023 | Gloucester | 3.8 |
| David Lloyd Leisure, Whittle Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Tewkesbury | 5.1 |
| Laithwaites Wines, Gloucester Business Parkrooftop solar | rooftop solar | 0.8 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Tewkesbury | 5.4 |
| Tbs Engineering, Gloucester Business Parkrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Tewkesbury | 5.4 |
| The Farm Consultancy Grouprooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Jul 2025 | granted Sep 2025 | Nov 2025 | Tewkesbury | 5.4 |
| Francis And Lewis International, Waterwells Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2022 | Aug 2022 | granted Nov 2022 | Dec 2022 | Gloucester | 5.5 |
| Alpha Colour Printers, Waterwells Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Gloucester | 5.5 |
| Hatherley Manor Hotel, Down Hatherley Lanerooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Sep 2022 | Aug 2022 | — | Sep 2022 | Tewkesbury | 5.5 |
| The Io Centre, Gloucester Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 | Tewkesbury | 5.5 |
| The IO Centre, Gloucester Business Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Dec 2023 | Jan 2024 | Tewkesbury | 5.5 |
| MG Markey Group, Quadrant Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | Stroud | 6.0 |
| Safran Landing System, Down Hatherley Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Tewkesbury | 6.3 |
| Anson Business Park, Cheltenham Road Eastrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Tewkesbury | 7.0 |
| Dobbies Garden Centres, Bath Roadrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Dec 2023 | Oct 2023 | — | Dec 2023 | Stroud | 8.1 |
| Leewayssolar farm | solar farm | 0.5 | operationalupdated Nov 2019 | Oct 2018 | granted Jan 2019 | Nov 2019 | Forest of Dean | 8.6 |
| Highleadon Solar Arrays & Battery Storagebattery storage | battery storage | — | operationalupdated Apr 2026 | Feb 2022 | granted Oct 2023 | Apr 2026 | Forest of Dean | 8.8 |
Distance from the average position of the GL1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 2 | 7 | 2 | 3 | 214 |
| Rooftop solar | 32 | 2 | 27 | 1 | 0 | 13.1 |
| Battery storage | 10 | 2 | 5 | 2 | 0 | 280 |
MW in pipeline: pending, approved and under-construction capacity.
How Gloucester decides solar, wind and battery applications
| Applications | Gloucester | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 1 (5%) | 19% |
| Solar refused | 1 of 17 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL1, 8 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.