Energy Projects Near You

Moreton Lane Solar Farm & Battery Storage (49.9 MW)

Moreton Lane Solar Farm & Battery Storage is a 49.9 MW solar farm project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 April 2022, not yet built; the record was last updated on 28 April 2022. REPD records the planning permission as expiring on 5 April 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
28 April 2022record last updated
Stroudcouncil area

REPD records the planning permission as expiring on 5 April 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
23 February 2021Application submitted
5 April 2022Planning permission granted
5 April 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
28 April 2022
Operator or applicant
JBM Solar Projects 7 Limited
Planning authority
Stroud
Planning application reference
S.21/0465/FUL
Site area
116.0 ha
Address (REPD)
Land Parcels A & B Near Whitminster Gloucestershire
Council area (by location)
Stroud
Time to decision
58 weeks
Contracts for Difference
AR5
Name in REPD
Moreton Lane - Solar Farm & Battery Storage
REPD reference
8843

The scheme also includes 49.9 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
High Green Longney Estate Solar Farmsolar farm25permission expired1.7
High Green Longney Estate Solar Farmsolar farm20permission expired1.7
Epney, Framilode Solar Farm & Battery Storagesolar farm49.5refused2.3
Brookthorpe Solar Farmsolar farm8approved, not built5.8
Gravel Farm, Cleeve Solar Farmsolar farm32application withdrawn6.2
Bristol Roadbattery storage20permission expired6.2
Stantway Solar Farmsolar farm5operational6.6
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn7.0
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7951, -2.3128).