Energy Projects Near You

Solar, wind and battery projects near Stroud (GL5)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL5 (Stroud): 1 is waiting for a planning decision, 12 approved but not yet running, 3 operational. The largest live scheme is Moreton Lane Solar Farm & Battery Storage (49.9 MW solar farm, approved on 5 April 2022, not yet built; REPD status may be out of date), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
1awaiting a decision
12approved, not running
3operational

Projects within 10 km of GL5

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Windmill Hillwind farmwind farm1.5refusedupdated Feb 2004Oct 2000refused May 2001Feb 2004Stroud4.9
Lynch Knoll Wind Farm (Extension)wind farmwind farm1.5appeal withdrawnupdated Jan 2010Oct 2000refused Dec 2000Jan 2010Stroud5.1
Delphi Diesel Systems, Brunel Wayrooftop solarrooftop solar1.6approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Stroud5.7
Fawkes 1solar farmsolar farm4.7refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015Stroud5.8
Fawkes 2 Solar Farmsolar farmsolar farm4.7refusedupdated Dec 2015Jul 2015refused Nov 2015Dec 2015Stroud6.0
Moreton Lane Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud8.9
Moreton Lane Solar Farm & Battery Storagebattery storagebattery storage49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud8.9
Unit Q1, Quadrant Distribution Centre, Hardwickrooftop solarrooftop solar1approved, not builtupdated May 2022Apr 2022granted May 2022May 2022Stroud9.1
Hillhouse Farmsolar farmsolar farm28.5operationalupdated Apr 2015Aug 2014granted Dec 2014Apr 2015Stroud9.7
Brookthorpe Solar Farmsolar farmsolar farm8approved, not builtupdated Feb 2026Apr 2024granted Dec 2024Feb 2026Stroud9.8
Land at Box Roadsolar farmsolar farm2.2operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Stroud9.9
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Science building, Dudbridge Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023Stroud1.0
Sainsburys Supermarket, Dudbridge Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Aug 2024—Aug 2024Stroud1.3
Wellington House, Bath Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2022Dec 2021Stroud3.6
A B B Limited, Oldends Lanesolar farmsolar farm0.8approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Stroud5.1
Renishaw PLC Factoryrooftop solarrooftop solar0.8operationalupdated May 2020Jun 2018granted Mar 2019May 2020Stroud5.5
Brunel Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Stroud5.6
Dobbies Garden Centres, Bath Roadrooftop solarrooftop solar0.2application withdrawnupdated Dec 2023Oct 2023—Dec 2023Stroud7.5
Francis And Lewis International, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Gloucester9.1
MG Markey Group, Quadrant Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Stroud9.1
Alpha Colour Printers, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Gloucester9.1

Distance from the average position of the GL5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7032258.7
Rooftop solar1118104.8
Wind farm200010
Battery storage1010049.9

MW in pipeline: pending, approved and under-construction capacity.

How Stroud decides solar, wind and battery applications

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Stroud

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL5, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.