Energy Projects Near You

Solar, wind and battery projects near Tetbury (GL8)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL8 (Cotswold): 3 are waiting for a planning decision, 4 approved but not yet running, 5 operational. The largest live scheme is Lime Down Solar Project (500 MW solar farm, application submitted on 17 October 2025, no decision recorded), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
3awaiting a decision
4approved, not running
5operational

Projects within 10 km of GL8

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Newnton Dairy Farmsolar farmsolar farm7.2operationalupdated Apr 2014Jun 2013granted Sep 2013Apr 2014Wiltshire4.4
Marsh Farmsolar farmsolar farm14operationalupdated Feb 2017Jul 2012granted Jan 2013Feb 2017Wiltshire4.6
Malmesbury Solarsolar farmsolar farm5operationalupdated Mar 2013Mar 2011granted May 2011Mar 2013Wiltshire4.8
Crudwell Road Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Feb 2026Mar 2021granted Aug 2023Feb 2026Wiltshire6.3
Lodge Farm (Poulshot)solar farmsolar farm14.5operationalupdated Apr 2015Oct 2013granted Feb 2014Apr 2015Wiltshire8.6
Windmill Hillwind farmwind farm1.5refusedupdated Feb 2004Oct 2000refused May 2001Feb 2004Stroud9.2
Lime Down Solar Projectsolar farmsolar farm500application submittedupdated Jun 2026Oct 2025—Jun 2026Wiltshire9.3
Lime Downbattery storagebattery storage500application submittedupdated Jun 2026Oct 2025—Jun 2026Wiltshire9.3
Lynch Knoll Wind Farm (Extension)wind farmwind farm1.5appeal withdrawnupdated Jan 2010Oct 2000refused Dec 2000Jan 2010Stroud9.4
Kemble Wicksolar farmsolar farm49.9operationalupdated Apr 2026Jul 2021granted Mar 2022Apr 2026Cotswold9.9
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Tetbury Audi, Quercus Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Cotswold1.5
Westonbirt Schoolrooftop solarrooftop solar—application withdrawnupdated Dec 2025Oct 2025—Dec 2025Cotswold4.6
Whitewalls, Easton Greyrooftop solarrooftop solar0.2application submittedJun 2026——Wiltshire6.3
Crudwell Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Apr 2021Mar 2021granted Aug 2023Apr 2021Wiltshire6.3
Wellington House, Bath Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2022Dec 2021Stroud8.0

Distance from the average position of the GL8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm71150550
Rooftop solar412000.7
Wind farm200010
Battery storage21100500

MW in pipeline: pending, approved and under-construction capacity.

How Cotswold decides solar, wind and battery applications

ApplicationsCotswoldUK
Decided applications (solar, wind, battery)2010,236
Refused2 (10%)19%
Solar refused2 of 1812%
Battery storage refused0 of 216%
Median time from submission to decision16.6 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

All projects in Cotswold

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL8, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.