Lime Down (500 MW battery storage)

Lime Down is a 500 MW battery storage project in Wiltshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 17 October 2025, no decision recorded; the record was last updated on 26 June 2026. As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010168).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
application submittedstatus in REPD
26 June 2026record last updated
Wiltshirecouncil area

Planning timeline

DateStage
17 October 2025Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
500 MW
Status (REPD)
application submitted
Record last updated
26 June 2026
Operator or applicant
Island Green Power
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010168
Address (REPD)
W/O Corston, N/O Hullavington, Chippenham
Council area (by location)
Wiltshire
Name in REPD
Lime Down - Battery Storage
REPD reference
16064

Recorded together with Lime Down Solar Project (500 MW solar farm, application submitted).

Official project record at the Planning Inspectorate (EN010168)

Who decides

As a nationally significant project, it is decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010168). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hullavington Solar Parksolar farm7operational3.1
Leigh Delamere Solar farm & Battery storagesolar farm49.9under construction6.1
Rodbourne Rail Farm Solar Parksolar farm7.6operational6.9
Castle Combe Circuitsolar farm12operational7.6
Red Barn Solar Farm & Battery Storagesolar farm40approved, not built8.4
Tiddlywink Barn Battery Storage Power Plantbattery storage20abandoned9.0
Solar Farm at East of Battens Farmsolar farm10approved, not built9.0
Crudwell Road Solar Farm & Battery Storagesolar farm49.9approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.561, -2.1993).