Energy Projects Near You

Solar, wind and battery projects near Badminton (GL9)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL9 (South Gloucestershire): 4 are waiting for a planning decision, 8 approved but not yet running, 4 operational. The largest live scheme is Lime Down Solar Project (500 MW solar farm, application submitted on 17 October 2025, no decision recorded), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
4awaiting a decision
8approved, not running
4operational

Projects within 10 km of GL9

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lime Down Solar Projectsolar farmsolar farm500application submittedupdated Jun 2026Oct 2025—Jun 2026Wiltshire7.2
Lime Downbattery storagebattery storage500application submittedupdated Jun 2026Oct 2025—Jun 2026Wiltshire7.2
Mounteneys and Cherry Rock Wind Turbineswind farmwind farm1operationalupdated May 2022Feb 2012—May 2022Stroud7.8
Castle Combe Circuitsolar farmsolar farm12operationalupdated Apr 2015Jul 2014granted Nov 2014Apr 2015Wiltshire9.1
Rag Lane Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Dec 2022Jan 2021granted Dec 2021Dec 2022South Gloucestershire9.3
Codrington Roadsolar farmsolar farm18.8approved, not builtupdated Jul 2022Oct 2022granted Aug 2023Jul 2022South Gloucestershire9.4
Mousewell Farm, Besom Lane Solar Farmsolar farmsolar farm22application submittedupdated Jan 2025Dec 2024—Jan 2025South Gloucestershire9.4
Hullavington Solar Parksolar farmsolar farm7operationalupdated May 2016May 2013granted Nov 2013May 2016Wiltshire9.7
Ring O Bells Farmsolar farmsolar farm5operationalupdated Oct 2016Jun 2014granted Aug 2015Oct 2016South Gloucestershire9.8
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hobs House Bakery, Hatters Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Nov 2023granted Dec 2023Dec 2023South Gloucestershire6.3
Larks Lane, Iron Actonbattery storagebattery storage—approved, not built may be out of dateupdated Oct 2021May 2021granted Jul 2021Oct 2021South Gloucestershire7.8
Yate Leisure Centre, Kennedy Wayrooftop solarrooftop solar0.4approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024South Gloucestershire8.0
Abbotswood Primary School, Kelston Closerooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026South Gloucestershire8.9
Westonbirt Schoolrooftop solarrooftop solar—application withdrawnupdated Dec 2025Oct 2025—Dec 2025Cotswold9.2
Mousewell Farm, Besom Lane Solar Farmbattery storagebattery storage—application submittedupdated Jan 2025Dec 2024—Jan 2025South Gloucestershire9.4
Talbot Farm, Dyrham Roadwind farmwind farm—approved, not builtupdated Jan 2026Apr 2025granted Dec 2025Jan 2026South Gloucestershire9.7
Renishaw Plc, Old Townrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Apr 2022Apr 2022granted May 2022Apr 2022Stroud9.8

Distance from the average position of the GL9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm72230591
Rooftop solar504001.1
Wind farm201100
Battery storage32100500

MW in pipeline: pending, approved and under-construction capacity.

How South Gloucestershire decides solar, wind and battery applications

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in South Gloucestershire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.