Energy Projects Near You

Ring O Bells Farm (5 MW solar farm)

Ring O Bells Farm is a 5 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 August 2016; the record was last updated on 3 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
3 October 2016record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
26 June 2014Application submitted
7 August 2015Planning permission granted
25 November 2015Construction started
18 August 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
3 October 2016
Operator or applicant
Green Energy UK Direct
Planning authority
South Gloucestershire
Planning application reference
PK14/2339/F
Site area
38.1 ha
Address (REPD)
Ring O Bells Farm Pucklechurch Road Hinton Chippenham South Gloucestershire SN14 8HJ
Council area (by location)
South Gloucestershire
Time to decision
58 weeks
REPD reference
2020

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Codrington Roadsolar farm18.8approved, not built3.1
Westerleigh Hill, Westerleighbattery storage200approved, not built3.7
Mousewell Farm, Besom Lane Solar Farmsolar farm22application submitted4.0
Says Court Farm solar parksolar farm19.8operational6.2
Says Court Farm, Coalpit Heathbattery storage50approved, not built6.2
Partfield Farmwind farm5.6application withdrawn7.8
Elm Farm solar farm and Battery storagesolar farm24refused8.6
Perrinpit Farmsolar farm49.9under construction9.4
Green Farmsolar farm9.4refused on appeal10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.489, -2.3961).