Partfield Farm (5.6 MW wind farm)

Partfield Farm is a 5.6 MW wind farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 8 May 2001; the record was last updated on 5 February 2004.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWwind farm
application withdrawnstatus in REPD
5 February 2004record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
9 October 2000Application submitted
8 May 2001Application withdrawn

Project details

Technology
wind farm
Capacity
5.6 MW
Status (REPD)
application withdrawn
Record last updated
5 February 2004
Operator or applicant
Ecotricity
Planning authority
South Gloucestershire
Planning application reference
S.00/1628
Address (REPD)
Partfield Farm, Nympsfield
Council area (by location)
South Gloucestershire
REPD reference
3276

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Feeder Roadbattery storage20operational4.9
Lockleaze Energy Storagebattery storage15operational5.0
Philip Street Car Breakersbattery storage7.2approved, not built5.1
Westerleigh Hill, Westerleighbattery storage200approved, not built5.8
Codrington Roadsolar farm18.8approved, not built7.5
Mousewell Farm, Besom Lane Solar Farmsolar farm22application submitted7.7
Ring O Bells Farmsolar farm5operational7.8
Grange Farm (Avon)solar farm21operational7.9
Hammond Court Farmsolar farm15operational7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4699, -2.5041).