Energy Projects Near You

Westerleigh Hill, Westerleigh (200 MW battery storage)

Westerleigh Hill, Westerleigh is a 200 MW battery storage project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 July 2024, not yet built; the record was last updated on 19 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
19 August 2024record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
29 March 2023Application submitted
19 July 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
19 August 2024
Operator or applicant
Immersa Limited
Planning authority
South Gloucestershire
Planning application reference
P23/01180/F
Address (REPD)
Land Off Westerleigh Hill Westerleigh
Council area (by location)
South Gloucestershire
Time to decision
68 weeks
Name in REPD
Westerleigh Hill, Westerleigh - Battery Energy Storage Facility
REPD reference
13607

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Codrington Roadsolar farm18.8approved, not built1.8
Mousewell Farm, Besom Lane Solar Farmsolar farm22application submitted2.0
Says Court Farm, Coalpit Heathbattery storage50approved, not built3.2
Says Court Farm solar parksolar farm19.8operational3.2
Ring O Bells Farmsolar farm5operational3.7
Elm Farm solar farm and Battery storagesolar farm24refused5.3
Partfield Farmwind farm5.6application withdrawn5.8
Perrinpit Farmsolar farm49.9under construction5.8
Green Farmsolar farm9.4refused on appeal6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5052, -2.443).