Energy Projects Near You

Says Court Farm solar park (19.8 MW)

Says Court Farm solar park is a 19.8 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2014; the record was last updated on 2 April 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWsolar farm
operationalstatus in REPD
2 April 2014record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
9 April 2013Application submitted
1 October 2013Planning permission granted
31 March 2014Operational

Project details

Technology
solar farm
Capacity
19.8 MW
Status (REPD)
operational
Record last updated
2 April 2014
Operator or applicant
AEE Renewables
Planning authority
South Gloucestershire
Planning application reference
PT13/1082/F
Site area
40.3 ha
Address (REPD)
Says Court Farm Badminton Road Coalpit Heath Bristol South Gloucestershire BS36 2NY
Council area (by location)
South Gloucestershire
Time to decision
25 weeks
REPD reference
1663

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Says Court Farm, Coalpit Heathbattery storage50approved, not built<0.1
Mousewell Farm, Besom Lane Solar Farmsolar farm22application submitted2.2
Elm Farm solar farm and Battery storagesolar farm24refused2.5
Codrington Roadsolar farm18.8approved, not built3.1
Westerleigh Hill, Westerleighbattery storage200approved, not built3.2
Perrinpit Farmsolar farm49.9under construction3.5
Green Farmsolar farm9.4refused on appeal3.8
Patch Elm Lanebattery storage35approved, not built4.1
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5336, -2.4494).