Perrinpit Farm (49.9 MW solar farm)

Perrinpit Farm is a 49.9 MW solar farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2025; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
5 August 2025record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
12 March 2021Application submitted
21 September 2022Planning permission granted
1 June 2025Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
5 August 2025
Operator or applicant
Grune Energien
Planning authority
South Gloucestershire
Planning application reference
P21/01624/F
Site area
90.0 ha
Address (REPD)
Land At Perrinpit Farm, Perrinpit Road, Frampton Cotterell, Bristol, Avon
Council area (by location)
South Gloucestershire
Time to decision
80 weeks
Contracts for Difference
AR5
REPD reference
7944

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Elm Farm solar farm and Battery storagesolar farm24refused1.4
Green Farmsolar farm9.4refused on appeal1.6
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built1.7
Grange Farm (Avon)solar farm21operational1.9
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built2.3
Hammond Court Farmsolar farm15operational2.5
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built2.5
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built2.6
Lower Larks Farmbattery storage99.9approved, not built2.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5453, -2.4969).