Energy Projects Near You

Earthcott Green Farm, Earthcott Green (200 MW battery storage)

Earthcott Green Farm, Earthcott Green is a 200 MW battery storage project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 July 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
19 August 2025record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
31 March 2023Application submitted
20 June 2024Refused by the planning authority
19 December 2024Appeal lodged
30 July 2025Planning permission granted
30 July 2025Appeal allowed

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Immersa Limited
Planning authority
South Gloucestershire
Planning application reference
P23/01244/F
Appeal reference
APP/P0119/W/24/3357847
Address (REPD)
Earthcott Green Farm, Earthcott Green, Alveston, Bristol
Council area (by location)
South Gloucestershire
Time to decision
122 weeks
Name in REPD
Earthcott Green Farm, Earthcott Green - Battery Energy Storage
REPD reference
13643

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built0.5
Alveston Wind Parkwind farm6.9operational1.1
Green Farmsolar farm9.4refused on appeal1.7
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built1.7
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built1.9
Lower Larks Farmbattery storage99.9approved, not built2.1
Perrinpit Farmsolar farm49.9under construction2.3
Larks Lane, Iron Actonbattery storage20application submitted2.3
Larks Green Solar Farmsolar farm70operational2.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.564, -2.5097).