Energy Projects Near You

Larks Lane, Iron Acton (20 MW battery storage)

Larks Lane, Iron Acton is a 20 MW battery storage project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 31 May 2023, no decision recorded; the record was last updated on 16 June 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
application submittedmay be out of datestatus in REPD
16 June 2023record last updated
South Gloucestershirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
31 May 2023Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
16 June 2023
Operator or applicant
HD000ACT Limited
Planning authority
South Gloucestershire
Planning application reference
P23/01616/F
Address (REPD)
E/O Larks Lane, E/O Larks Lane, Bristol
Council area (by location)
South Gloucestershire
Name in REPD
Larks Lane, Iron Acton - Battery Storage Facility
REPD reference
14091

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Larks Farmbattery storage99.9approved, not built0.2
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built0.5
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built0.6
Larks Green Solar Farmsolar farm70operational0.9
Patch Elm Lanebattery storage35approved, not built0.9
Green Farmsolar farm9.4refused on appeal1.4
Alveston Wind Parkwind farm6.9operational1.5
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built2.3
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5699, -2.4779).