Alveston Wind Park (6.9 MW)

Alveston Wind Park is a 6.9 MW wind farm project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 7 December 2017; the record was last updated on 13 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.9 MWwind farm
operationalstatus in REPD
13 December 2017record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
2 June 2008Application submitted
13 November 2008Planning permission granted
8 October 2015Construction started
7 December 2017Operational

Project details

Technology
wind farm
Capacity
6.9 MW
Status (REPD)
operational
Record last updated
13 December 2017
Operator or applicant
Ecotricity
Planning authority
South Gloucestershire
Planning application reference
PT08/1658/F
Turbines
3
Turbine height
100 m
Address (REPD)
Land off Old Gloucester Road, Nr Alveston, South Gloucestershire
Council area (by location)
South Gloucestershire
Time to decision
23 weeks
REPD reference
4335

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Iron Acton Substation, Latteridge Lanebattery storage99approved, not built1.1
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built1.1
Lower Larks Farmbattery storage99.9approved, not built1.4
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built1.4
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built1.5
Larks Lane, Iron Actonbattery storage20application submitted1.5
Larks Green Solar Farmsolar farm70operational1.7
Green Farmsolar farm9.4refused on appeal1.8
Patch Elm Lanebattery storage35approved, not built2.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5723, -2.4999).