Iron Acton Substation, Latteridge Lane (99 MW battery storage)

Iron Acton Substation, Latteridge Lane is a 99 MW battery storage project in South Gloucestershire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 August 2024, not yet built; the record was last updated on 6 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
approved, not builtstatus in REPD
6 September 2024record last updated
South Gloucestershirecouncil area

Planning timeline

DateStage
21 August 2023Application submitted
16 August 2024Planning permission granted
16 August 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
approved, not built
Record last updated
6 September 2024
Operator or applicant
Balance Power Projects Limited
Planning authority
South Gloucestershire
Planning application reference
P23/02405/F
Address (REPD)
West Of Iron Acton Substation Latteridge Lane Iron Acton
Council area (by location)
South Gloucestershire
Time to decision
52 weeks
Name in REPD
Iron Acton Substation, Latteridge Lane - Battery Energy Storage System
REPD reference
14722

Who decides

ApplicationsSouth GloucestershireUK
Decided applications (solar, wind, battery)7910,236
Refused7 (9%)19%
Solar refused3 of 5912%
Onshore wind refused2 of 445%
Battery storage refused2 of 1616%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Larks Lane & Latteridge Lane, Latteridgebattery storage49.9approved, not built0.4
Lower Larks Farmbattery storage99.9approved, not built0.4
Larks Lane, Iron Actonbattery storage20application submitted0.6
Green Farmsolar farm9.4refused on appeal1.1
Alveston Wind Parkwind farm6.9operational1.1
Larks Green Solar Farmsolar farm70operational1.3
Patch Elm Lanebattery storage35approved, not built1.5
Earthcott Green Farm, Earthcott Greenbattery storage200approved, not built1.7
Old Green Farm, Alveston Battery Storagebattery storage10approved, not built1.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.568, -2.4861).